Which statement accurately depicts what changes can be made to requirements after they are baselined?
A. Requirements can be changed through a defined process.
B. Requirements cannot be changed once development begins.
C. Requirements cannot be changed once user acceptance testing begins.
D. Requirements can be changed only with sponsor approval.
A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?
A. Meet with the stakeholder and discuss timeline impact.
B. Define a requirements baseline and implement a change control process.
C. Implement only the original requirements.
D. Refer changes to the project manager.
During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?
A. Organization modeling
B. Power/interest grid
C. Business activity model
D. RACI matrix
Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company's performance and profitability.
Which of the following should have been implemented to ensure that the projects would improve the company's performance and profitability?
A. A risk plan
B. A strategies and goals analysis
C. A project management plan
D. A review with appropriate stakeholders
An insurance company embarks on a project to replace its current enrollment and billing software application, which will no longer be supported by the end of the calendar year. The new enrollment and billing application must be implemented before the current vendor contract ends. The business analyst gathers the initial requirements for the new enrollment and billing application. Based on the large volume of requirements, the business analyst realizes that the requirements will need to be prioritized. Which requirements prioritization method should the business analyst use for this project?
A. Time-boxing
B. Risk analysis
C. Weighted ranking
D. MoSCoW
The best way to ensure the integrity of requirements is to:
A. implement version control, maintain a history of requirements changes, and track the status of each requirement
B. establish a requirements baseline, establish a change control board, and label each requirement uniquely
C. use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes
D. establish a change control board, track the status of each requirement, and use a requirements management tool.
The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.
This situation could have been averted if:
A. critical business requirements were accommodated and tested.
B. essential product requirements were captured and tested.
C. quality attributes were captured and tested.
D. nonfunctional requirements were identified and tested.
Testing on a project has been completed. In order to proceed with deployment, a decision is needed.
Who should the business analyst contact to review the testing results and get approval to proceed with deployment?
A. The tester identified in the testing strategy
B. The project manager identified in the project charter.
C. The project sponsor identified in the scope document.
D. The person identified in the RACI matrix.
A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?
A. Consult
B. Responsible
C. Accountable
D. Inform
Which of the following actions will contribute most to the success of the initial stage of the project?
A. Interview stakeholders to clearly define the problem.
B. Establish the change control process of the project.
C. Define the acceptance criteria required during the acceptance phase.
D. Document the requirements and obtain sign-off.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-PBA exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.