Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
A. and the project board are responsible
B. and the team manager(s) are accountable
C. has responsibility
D. decides who is responsible
Which is a minimum requirement for applying the quality theme?
A. Appraisal methods of quality control must be carried out on products
B. A record must be kept of all the quality management activities that are planned
C. The quality review technique must be used when reviewing products
D. The quality management approach must align with corporate standards
Which process monitors work that has been assigned to a team manager?
A. Controlling a stage
B. Directing a project
C. Managing a stage boundary
D. Managing product delivery
Which describes an off-specification?
A. An interdependency between products that was previously unidentified
B. The addition of an improvement to a product description
C. A prototype demonstrating a possible design solution
D. The production of more than the defined quantity of a specialist product
Which is an objective of the 'managing a product delivery' process?
A. To ensure the business case is regularly reviewed
B. To assess whether the stage products have been approved
C. To deliver the planned specialist products within tolerance
D. To request authorization to start the next stage
What must be produced to meet the minimum requirements for applying the change theme?
A. Documentation on the corrective action for an issue
B. Details of the decisions taken on all issues
C. Documentation on the version of each product
D. Details of the status of all products being produced
Where should decisions regarding the tailoring of the project be recorded?
A. Project brief
B. Project initiation documentation
C. Project mandate
D. Stage plan
How does the project board use the 'manage by stages' principle to control the project?
A. By approving the project management team
B. By reviewing project viability at defined intervals
C. By ensuring that the benefits are managed and controlled
D. By reviewing previous project closure documentation
The application of which principle helps to define what should be included in a project?
A. Defined roles and responsibilities
B. Focus on products
C. Manage by stages
D. Continued business justification
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
A. when a stage plan has been prepared for
B. at the beginning of
C. when all the delivery steps have been completed within
D. at, or close to the end of,
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.