Which are objectives of the 'managing a stage boundary' process?
1.
To control the link between the people managing the project and the people producing the products
2.
To approve requests for change received during the completed stage
3.
To provide information to the project board on the performance of the current stage
4.
To review and, if necessary, update the project management team structure and role descriptions
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
What is a supplier of a PRINCE2 project responsible for?
A. Providing the project mandate
B. Providing resources to deliver the project outputs
C. Establishing the project's governance
D. Realizing the benefits from the project
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
A. At the start of the project
B. Throughout each stage
C. When a change is raised
D. In exception situations
Which is a purpose of the 'initiating a project' process?
A. To produce a stage plan for each stage of a multi-stage project
B. To enable the project board to decide whether it is worthwhile to initiate a project
C. To provide a fixed point at which acceptance for the project product is confirmed
D. To enable an organization to understand the work needed to deliver the project's products
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
A. change authority
B. project assurance
C. project support
D. senior user
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
A. Directing a project
B. Managing product delivery
C. Managing a stage boundary
D. Initiating a project
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
When should the level of tailoring be defined?
A. During the initiation stage
B. When reviewing what has been learned to date
C. As a response to issues and risks experienced
D. Before the project is triggered by the project mandate
Which is an objective of the 'initiating a project' process?
A. To ensure that baselines are established and controlled
B. To ensure that the business case is kept under review
C. To ensure that the planned products are delivered within tolerances
D. To ensure that user acceptance of the products is confirmed
Which is an objective of the 'starting up a project' process?
A. To approve the initiation stage
B. To select the project mandate
C. To define the project quality management approach
D. To appoint the project management team
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.