Within which integrated element does PRINCE2 set minimum requirements?
A. Themes
B. Processes
C. Principles
D. Project environment
Which is a purpose of the 'controlling a stage' process?
A. To produce a team plan for the work to be assigned to a team manager
B. To select and implement actions that will resolve deviations from a plan within tolerance
C. To obtain approvals for products delivered in a work package
D. To update a project plan to incorporate the actuals from a stage plan
What is performed as part of the recommended risk management procedure?
A. A budget to investigate issues is allocated
B. Risk management practices are reviewed to ensure that they are performed effectively
C. Information about risks to the projects is sent to project stakeholders
D. Conflicts between the project and the programme board are resolved
Which are purposes of the quality theme?
1.
To implement continuous improvement during the project
2.
To establish how the project will ensure that products created will be acceptable to key stakeholders
3.
To ensure that the project is desirable and achievable
4.
To identify, assess and control uncertainty
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Which product identifies how often stakeholders require information?
A. Communication management approach
B. Quality management approach
C. Change control approach
D. Risk management approach
What is a benefits management approach used to assess?
A. How the project's products have performed when in operational use
B. The effectiveness of the project strategies
C. How the project has progressed against its plans
D. The suitability of the project management team structure
Why is the 'initiating a project' process used?
A. To decide which project approach is suitable for the project
B. To fully understand how the project objectives will be achieved before committing significant resources
C. To produce the required work packages
D. To enable corporate or programme management to give authorization to deliver a project
Which is a purpose of the 'managing a stage boundary' process?
A. To enable the project board to approve the continuation of the project
B. To exercise overall control over the project while delegating day-to-day management
C. To assign work to be controlled by the team manager
D. To define the work that needs to be done to deliver the project product
According to PRINCE2, why might there be more than one business case for a project?
A. There may be more than one management stage in the project
B. The project may be in a commercial environment with a number of suppliers
C. There may be more than one work package being delivered in the project
D. The project may be in a programme environment
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
A. The senior user's responsibilities for realizing benefits
B. Statements of actual versus forecast benefits at reviews
C. The management actions needed to ensure benefits are realized
D. No specific documents related to benefits are necessary
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.