Note the checkboxes to the left-hand side of each project. If you uncheck a box, then that project will be removed from the totals displayed. This will also remove that project from the accompanying portfolio view.
Question 22:
Identify two available portfolio chart views in Primavera P6.
A. GANTT
B. Bubble
C. Histogram
D. Spreadsheet
E. Scorecard
Correct Answer: BC
Explanation:
B: Bubble Chart is the most complex and powerful portfolio view.
C: Histograms
Note that this is not a true histogram,
which is a diagram representing a distribution of data. An example of a true histogram would be a chart showing the number of activities completed each month.
Histograms in the Portfolio Analysis view are rather a "Relative order of Magnitude" chart presented as an X-Y chart.
Question 23:
You are a program manager reviewing portfolio performance data. You see that many issues are assigned to a "responsible manager." What does "responsible manager" mean with Primavera P6 EPPM?
A. The person responsible for resolving the issue
B. The person who identified the issue
C. The element from the OBS associated with the issue
D. the manager to which the issue has been assigned
Correct Answer: C
Explanation:
Your organization, from top-level personnel down through all levels. You can associate the responsible managers with their areas of the EPS-- either nodes or
individual projects. When you associate a responsible manager with an EPS node, any projects you add to that branch of the EPS are assigned that manager
element by default.
Note: Note: When you associate a responsible manager with an EPS Node, any projects you add to that branch of the EPS are assigned that manager element by
default. When you create a user, you have to give them Responsible Manager assignments in order for them to see projects. Your EPS and your OBS need to have a one-to-one relationship. If you give a user a Responsible Manager assignment (OBS) that is not tied to an EPS, Project or WBS level, they will not see any projects when they log into the Primavera Client application or the Web Application.
Question 24:
You are a P6 administrator. You have received a change request against a configured global dashboard, involving the addition of a portlet. How would you make this change?
A. Customize the user interface view
B. Customize the Portfolio view
C. Customize the dashboard
D. Customize the layout
Correct Answer: C
Explanation:
Add the portlet to the Dashboard.
Note:
*
Dashboards are created with up to 12 windows of data called Portlets
*
Dashboards build upon those analysis tools and present project and portfolio information in a way that is easy to set up and use. These dashboards can be customized and assigned so that specific users or groups of users can see the same information when they log into the system. Dashboards can be configured to suit individual needs or literally get everyone on the same page.
Question 25:
Identify the true statement regarding the EPS page in P6 R8.
A. You can copy a project on the EPS page and paste it into another EPS node.
B. You cannot copy projects on the EPS page - this must still be done in the Client.
C. Any user can now copy projects on the EPS page regardless of the user's Security profile.
D. Only application administrators have the privilege to copy/paste projects.
Correct Answer: A
Explanation:
Note:
*
Enterprise Project Structure (EPS)
The EPS is the outsider's view of your company, showing your lines of business. The EPS is laid out in a tree structure.
*
Simply put, "enterprise" means information that is shared across all projects.
Question 26:
Identify two business use case for templates.
A. Document standard operating processes
B. Customized projects for each user in each organization
C. Facilitate scheduling standards for projects requiring audits
D. Enhanced resource management and capacity planning
E. Top-down budgeting and costed actuals
Correct Answer: AC
Explanation:
Templates facilitates standards.
*
With templates, you do not have to start over at step one each and every time you have a new project. This is particularly helpful when you are working in an environment with many users, resources, and/or projects as it gives repeatability and consistency to projects in your organization.
*
Templates allow a user to begin with a framework
of WBS, activities, and other project data to ensure that new projects are consistent, have repeatable quality results, and that they comply with internal and external standard procedures.
Question 27:
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this.
A. Create a Secure Global Activity Code.
B. Create a Global Security Privilege for the Governance organization.
C. Create a Global Governance Activity view.
D. Group and sort by Governance deliverable.
E. Create a filter available to the Governance organization.
F. Create a custom portlet for a Governance dashboard.
Correct Answer: ACE
Explanation:
Filter on the Global Activity Code and display in the activity view.
Question 28:
You are a project manager on a fixed-bid contract. This contract has actually been positioned as a "loss leader" within your company because it is your first contract with this customer. The hope is that you can prove yourself to the customer and win additional business at higher margins down the road. The margins for this contract are very slim.
What would be the best solution to set up in P6 to give you the visibility that you need to minimize the probable financial loss?
A. Set a Mandatory Finish constraint at each contractual milestone and track schedule performance against the constraint.
B. Set all activities in your project plan to Physical % Complete, and use Remaining Duration to track schedule performance.
C. Set all activities in your project plan to Units % Complete, and use Remaining units to track schedule performance
D. Set a Must finish By date at the project level, and track schedule performance using float in the project plan.
Correct Answer: B
Explanation:
Note: Percent complete
You can also update activity status by entering the completed percentage against it. In the Activity Details screen, you can set the percentage complete for the
activity to be one of these three types:
· Duration: It simply calculates the current date versus the start date and planned duration.
· Physical: It requires statusing both resource units (remaining duration or percent complete). This delivers a better representation of progress, but at the cost of
requiring greater detail.
· Units: It requires statusing of remaining units. The percent of delivered units compared to planned units drives progress for the activity.
Question 29:
In your project, cost and work effort is not subject to change. Which duration type should be used?
A. Fixed Units
B. Fixed Duration and Units/Time
C. Fixed Units/Time
D. Fixed Duration and Units
Correct Answer: A
Explanation:
Cost and work is here least flexible. If total work effort or fixed costs are most important, choose Fixed Units.
Note: Working with Duration Types
Duration type options
Duration type determines whether the schedule, resource availability, or cost is most inflexible when calculations are performed to reflect activity progress.
Duration type affects update calculations only when resources are assigned to an activity.
Choose a duration type based on which factor is the most important, or least flexible, in planning your project.
If schedule is most important, choose Fixed Duration and Units/Time or Fixed Duration and Units. If resource availability is most important, choose Fixed Units/
Time. If total work effort or fixed costs are most important, choose Fixed Units.
Question 30:
Where are workflows accessed?
A. In portfolios
B. In the EPS
C. In the dashboards
D. In the workspace
Correct Answer: C
Explanation:
The Workflow portlet is displayed in a Dashboard.
Example:
1) Setup and Configuration: After your administrator sets up BPM, configure a dashboard to display the Workflows portlet.
2)Action Required Tab: This tab shows the tasks that are important to you (the currently logged in user).
3)My Workflows Tab: This tab enables you to view all workflows according to role and status filters you can set.
4) Initiate a Workflow: Click Initiate a Workflow to start a new instance of a workflow based on a predesigned template.
Note:
When a specific user or any user assigned to a role or group logs into P6, the Workflows portlet on their dashboard will display their relevant tasks at this stage of
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-567 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.