You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there.
What happened?
A. You no longer have sufficient project-level security to view the "missing" project's data.
B. Your web interface license was revoked to allow other users to interface with the projects.
C. The value of the code assigned to the missing projects has changed.
D. The projects were deleted when the filter was refreshed.
You are developing a reporting strategy for a customer who requires monthly reports showing cost variance. The customer has two requirements.
1.
Each report must come from Primavera.
2.
Each month's report must become a "snapshot" for legal traceability purposes.
Which P6 R8 solution addresses each of the customer's requirements?
A. Email monthly report to distribution list
B. Send reports directly to printers at all user locations
C. Archive printed reports in files under security
D. Send generated report to content repository
Select the true statement regarding live or summarized data.
A. Live data is used for resource management.
B. Live data is used for portfolio management.
C. Summarized data is used for resource management.
D. Summarized data is used for project management.
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You are doing an audit prior to a gate review for a specific project. You are fairly certain that the project manager and project are in compliance with these requirements, but you cannot see the required work products and documents in the project workspace. How can you solve this problem?
A. Go to Activities and search tor the Work Products and Documents by using an Activity view.
B. Go to a dashboard and look for the Work Products and Documents in a portlet.
C. Create a global activity code for required Work Products and Documents to call out activities.
D. Go to the Project section and click Work Products and Documents to view the portlet.
You are an implementation consultant responding to the requirement that a cost account structure be set up in Primavera to be able to receive actual costs incurred by each contributing organization. There is also a cost account structure set up in the customer's financial management system (FMS).
What would be the easiest long-term recommendation for setup and maintenance of the cost account structure?
A. Set up a cost account structure in Primavera that mirrors the FMS, and manually manage changes.
B. Set up a cost account structure in Primavera and a global project code to map to FMS for Integration.
C. Do not set up the cost account structure, and receive costed actuals only from the FMS.
D. Set up integration between Primavera and the FMS to maintain all ongoing costing data.
You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops. The "projects" theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it becomes clear that the projects are not really multi-year projects. The plans have been managed by creating "new" projects within the old projects by skipping a few lines in what has become more of a program history.
What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?
A. Import all MS Project plans directly into the P6 production database "as is."
B. Import MS Project plans but break out current in-flight work into separate projects.
C. Create new projects only for in flight work identified in MS Project plans.
D. Retire legacy project plans and start with new project planning standards.
Identify the true statement regarding user-interface views.
A. Deleting a user-interface view that has assigned users could cause user issues.
B. Each user may be assigned to multiple user-interface views.
C. User-interface views overwrite project and global security profiles.
D. User-interface views are created and managed by individual users.
Identify the best definition of the EPS.
A. The hierarchical definition of project budgets and actual costs.
B. The hierarchical definition of reporting structures.
C. The hierarchical structure of the security for projects.
D. The hierarchical structure of the database of projects.
You received an e-mail from a portfolio manager asking you to check performance metrics for the past months on each of the projects filtered for that portfolio.
You cannot locate the portfolio that the email references.
What is the probable cause?
A. It is a user portfolio created by the portfolio manager.
B. It is a user-filtered portfolio that has not been refreshed.
C. You do not have the appropriate license for the web interface.
D. You have not been assigned as a resource to the projects.
Where are risk response plans captured?
A. In the Risk Scoring Matrix
B. In the Activity Notebook for Risk
C. In the Risk Register
D. In the Project Notebook for Risk
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-567 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.