In the plan Phase, Which of the following is a deployment project management task?
A. Review Logical, system and user design
B. Collect and verify project management plan requirements
C. Develop Backup/Recovery
D. Obtain and review security procedures
E. Analyze current infrastructure and propose new solution
Which Service Component within the prepare phase helps customers make a sound decision by providing information relating to financial justification and benefits?
A. Operations Technology Strategy Development
B. Business Requirements Development
C. Proof of Concept
D. Business Case Development
E. Technology Strategy Development
Which three tasks in the implement phase are contained in the IPC project Plan Template? (Choose three.)
A. Log Network Events
B. Define and Document Project Scope
C. Develop Backup/Recovery Plan
D. Identify Risks and Risk Mitigation Plans
E. Determine Vertical Approach and Strategy
F. Determine Project Schedule
It is important to help the customer establish an optimized process to identify areas for improvement under the optimization guidelines. What are two guideline best practices? (Choose two.)
A. Process output
B. Site Preparation
C. Rollback
D. Backup
Which tasks is performed during the site readiness assessment gap analysis in the plan phase?
A. Document Location of Legacy Equipment
B. Document Bandwidth Requirements for each site
C. Compare Systems Requirements specific to site survey
D. Assess and Document infrastructure requirements for the proposed solution
E. Determine if circuit can support required current calls
In the operate phase, the task of analyzing process exceptions belongs to which service component?
A. Problem Management
B. Incident Management
C. Change Management
D. Service Assurance
E. Security Administration
In the implement phase, project planning comprises which of the following tasks?
A. Update and document logical and physical topology maps and serial numbers
B. Confirm project and milestone dates, as well as project and cutover roles and responsibilities
C. Install,configure, and provision core products
D. Confirm deployment team, craft project plan,create communication and escalation plans
In the design phase, which template or tool is used to complete the schedule station reviews with user group task?
A. Operational Assessment Checklist
B. As Built Documentation
C. Business Requirements Document
D. Bill of Materials
E. Low Level Design
Developing a plan that identifies specific activities required to take existing services and network architectures and implement them on a new platform or as new services is an activity of which service component in the design phase?
A. Business Requirements Documents
B. Implementation Plan
C. Migration Plan Development
D. Detailed Design Development
E. Business Plan
F. Staging Plan
Your work as a network technician at Certkiller .com. Your boss, Mrs. Certkiller, is interested in Readiness
Assessment activities. You are required to select the correct five.
Choose five.
A. Circuit analysis
B. Onsite operational assessment
C. Call processing Assessment
D. Perform Application Assessment Gap Analysis
E. Security Analysis
F. Data and Voice Infrastructure Site Surveys
G. Traffic Analysis
H. Perform Voice and Data Gap Analysis
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Cisco exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 650-251 exam preparations and Cisco certification application, do not hesitate to visit our Vcedump.com to find your solutions here.