Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :Mar 25, 2025

PMI PMI Certifications CAPM Questions & Answers

  • Question 1201:

    Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

    A. Resource breakdown structure

    B. Physical resources assignment

    C. Team building activities

    D. Integrated Change Control

  • Question 1202:

    In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

    A. The receiver decodes the message

    B. The receiver responds to the message with feedback.

    C. The receiver transmits the message

    D. The receiver acknowledges their receipt of the message

  • Question 1203:

    What is a key benefit of using virtual project teams?

    A. Ensures appropriate behavior, security, and the protection of proprietary information

    B. Reduces the risk of conflict due to interpersonal communications and other interactions

    C. Assures that all team members have a clear and common understanding of the project

    D. Reduces project cost by use of modern technologies allowing seamless team collaboration

  • Question 1204:

    Which of these is a hybrid contract?

    A. Cost plus award fee (CPAF)

    B. Firm fixed price (FFP)

    C. Fixed price incentive fee (FPIF)

    D. Time and material (TandM)

  • Question 1205:

    Which is a key skill set in PMI's Talent Triangle?

    A. Project excellence and scope management

    B. Strategic and business management

    C. Scope management and business management

    D. Financial management and people management

  • Question 1206:

    Which is an aspect of the requirements management plan?

    A. Detailed project scope statement

    B. Creation of work breakdown strucure (WBS)

    C. Impact analysis

    D. Duration for implementation

  • Question 1207:

    A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

    What type of procurement document is the RFP?

    A. Bid document

    B. Statement of work (SOW)

    C. Source selection criteria

    D. Independent cost estimate

  • Question 1208:

    Which of these statements is true of subsidiary management plans?

    A. Subsidiary management plans are mandatory for any project

    B. Subsidiary management plans use the project charier as input

    C. Subsidiary management plans can be independently managed

    D. Subsidiary management plans do not need regular updates

  • Question 1209:

    When can we say that a project is completed?

    A. When the planned time duration is completed

    B. When the project objectives have been reached

    C. When the project manager has left the team

    D. When the project team decides to stop the work on the project

  • Question 1210:

    What behavior refers to leadership style?

    A. Do things right.

    B. Do the right things

    C. Ask how and when.

    D. Rely on control

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.