A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
A. Push communication
B. Pull communication
C. Interactive communication
D. Stakeholder communication
Recognition and rewards are tools and techniques of which process?
A. Develop Team
B. Manage Team
C. Control Resources
D. Plan Resource Management
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
A. Create Work Breakdown Structure (WBS)
B. Create Scope Baseline
C. Collect Requirements
D. Define Scope
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders.
What is this an example of?
A. Informal communication
B. Internal communication
C. Formal communication
D. Horizontal communication
What charts and figures should project managers use during the Perform Quantitative Risk Analysis process?
A. Tornado diagrams and influence diagrams
B. Detectability bubble charts and probability and impact matrix
C. Hierarchical charts and burndown charts
D. Flow charts and responsible, accountable, consult, and inform (RACI) charts
The document that guides project execution, monitoring and control, and closure is called:
A. The project charter
B. The project management plan
C. The integration plan
D. The execution plan
What communication methods would a project manager use for overall effective project communication?
A. Interactive communication, push communication, interpersonal communication
B. Interactive communication, push communication, pull communication
C. Push communication, pull communication, interpersonal communication
D. Pull communication, interactive communication, interpersonal communication
Using the following information and assuming that the project team will work a standard 40-hour work week:
Activity A has a duration of 10 days.
Activity B has a duration of 10 days and its predecessor is Activity A. Activity C has a duration of 15 days and its predecessor is Activity A. Activity D has a duration of 10 days and its predecessor is Activity B and C. Activity E has a duration of
10 days and its predecessor is Activity D. Activity F has a duration of 15 days and its predecessor is Activity D.
What is the critical path of the project?
A. ABDE
B. ACDF
C. ABDF
D. ACDE
When should Project Risk Management be conducted?
A. Project Planning
B. Monitoring and Controlling
C. Quality Planning
D. Throughout the project lifecycle
Project managers play a key role in performing integration on a project. What are the three different levels of integration?
A. Process, cognitive, and context
B. Complexity, understand, and change
C. Interact, insight, and leadership
D. Communication, knowledge, and value
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.