  • Question 181:

    A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

    A. Finish-to-Finish (FF)

    B. Start-to-Finish (SF)

    C. Finish-to-Start (FS)

    D. Start-to-Start (SS)

  • Question 182:

    A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

    A. Collective decision making

    B. Multicriteria decision analysis

    C. Mind mapping

    D. Affinity diagram

  • Question 183:

    In which organizational structure would the project manager have most authority?

    A. Matrix-weak

    B. Matrix-balanced

    C. Matrix-strong

    D. Organic or simple

  • Question 184:

    What are the objectives of initiation processes?

    A. Initiation processes are performed in order to develop the project charter and identify stakeholders.

    B. Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

    C. Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.

    D. Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

  • Question 185:

    Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

    A. List of identified risks, potential risk owners, list of potential risk response

    B. List of identified risks, list of causes, list of risk categories

    C. Short risk titles, list of potential risk owners, list of impacts on objectives

    D. List of activities affected, list of potential risk responses, list of causes

  • Question 186:

    One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

    A. It represents how and when the project will deliver the products, services, and results defined in the project scope

    B. It creates a formal record of the project and shows the organizational commitment to the project

    C. It describes how the scope will be defined, developed, monitored, controlled, and validated

    D. It provides the needs of a stakeholders or stakeholder group

  • Question 187:

    Which of the following sets are inputs to the Collect Requirements process?

    A. Project charter and requirements documentation

    B. Project charter and business documents

    C. Project charter and stakeholder requirements

    D. Business documents and requirements traceability matrix

  • Question 188:

    In which of the Risk Management processes is the project charter used as an input?

    A. Plan Risk Responses

    B. Implement Risk Responses

    C. Plan Risk Management

    D. Perform Quantitative Risk Responses

  • Question 189:

    Responsible, accountable, consult and inform (RACI) is an example of which of the following?

    A. Text-oriented format

    B. Resource management plan

    C. Organization chart

    D. Responsibility assignment matrix (RAM)

  • Question 190:

    An organizational structure that standardizes the project-related governance and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

    A. Project Management Information System

    B. Project Management System

    C. Project Management Office

    D. Project Management Knowledge Area

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.