A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
A. What-if scenario analysis
B. Simulation
C. Alternatives analysis
D. Reserve analysis
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A. Plan Quality Management
B. Control Quality
C. Risk Management
D. Plan Scope Management
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback was used to refine the requirements.
What technique is the team using?
A. Early requirements gathering
B. Feedback analysis
C. Progressive elaboration
D. Requirements documentation
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A. Risk, resource, and communications management plans
B. Scope, quality, and resource management plans
C. Procurement, integration, and risk management plans
D. Communications, schedule, and cost management plans
Which of these is true of project integration management?
A. Project Integration Management is mandatory and more effective in larger projects
B. Project Integration Management and expert judgment are mutually exclusive
C. Project Integration Management is the responsibility of the project manager
D. Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero
What does an S-curve from a Monte Carlo analysis show?
A. Cumulative probability distribution representing probability of achieving a particular outcome
B. Individual project risks or uncertainties that have the most potential impact on outcome
C. Best alternative out of the possible solutions, incorporating associated risks and opportunities
D. Diagram for all project uncertainties and their influence over a period of time
For which kind of quantitative risk analysis chart can a tornado diagram represent values?
A. Sensitivity analysis
B. Monte Carlo analysis
C. Expected monetary value analysis
D. Decision tree analysis
The focus on continuous communication with all stakeholders, including team members, is part of this knowledge area:
A. Project Integration Management
B. Project Resource Management
C. Project Stakeholder Engagement plan
D. Project Communications Management
A project manager is identifying the risks of a project. Which technique should the project manager use?
A. Representations of uncertainty
B. Prompt lists
C. Audits
D. Risk categorization
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?
A. Review stakeholder register and meeting
B. Data analysis and communication skills
C. Data gathering and data analysis
D. Communication skills and cultural awareness
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.