When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?
A. Iterative scheduling with backlog
B. On-demand scheduling
C. Life cycle scheduling with backlog
D. Defining iterative activities
In an agile or adaptive environment, when should risk be monitored and prioritized?
A. Only during the Initiation and Closing phases
B. During the Initiation and Planning phases
C. During each iteration as the project progresses
D. Throughout the Planning process group and retrospective meeting
What are the inputs of the Estimate Costs process?
A. Project management plan, work performance data, enterprise environmental factors, and organizational process assets
B. Project management plan, project documents, enterprise environmental factors, and organizational process assets
C. Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
D. Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Which is a list of organizational systems that may have an impact on a project?
A. Internal policies, company procedures, and organizational resources
B. Company culture, purchasing system, and project management information system
C. Organizational structure, governance framework, and management elements
D. Organizational process assets, enterprise environmental factors, and corporate knowledge
Which statement describes the relationship between Manage Quality process and Control Quality process?
A. Manage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
B. Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.
C. Manage Quality and Control Quality are the same.
D. Manage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.
How should a project manager plan communications for a project which has uncertain requirements?
A. Include stakeholders in project meetings and reviews, use frequent checkpoints, and co-locate team members only.
B. Invite customers to sprint planning and retrospective meetings, update the team quickly and on a daily basis, and use official communication channels.
C. Adopt social networking to engage stakeholders, issue frequent and short messages, and use informal communication channels.
D. Adopt a strong change control board process, establish focal points for main subjects, and promote formal and transparent communication.
Under which circumstances should multiple projects be grouped in a program?
A. When they are needed to accomplish a set of goals and objectives for an organization
B. When they have the same project manager and the same organizational unit
C. When they have the same scope, budget, and schedule
D. When they are from the same unit of the organization
Which task will a project manager undertake while conducting Project Resource Management?
A. Identify the different aspects of the team to manage and control physical resources efficiently
B. Procure equipment, materials, facilities, and infrastructure for the project
C. Train the team members in project skill sets
D. Define the roles and responsibilities of each team member
A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
A. Bottom-up estimating
B. Three-point estimating
C. Analogous estimating
D. Parametric estimating
Which of the following set of items belongs to the communications management plan?
A. Escalation processes and meeting management
B. Project schedule and glossary of common terminology
C. Escalation processes and stakeholder communication requirements
D. Interactive communication model and information to be communicated
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.