Which are required to create the schedule management plan?
A. Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list
B. Resource management plan, organizational process assets, activity list, and business case
C. Enterprise environmental factors, organizational process assets, project charter, and project management plan
D. Activity list, project statement of work, project charter, and communications management plan
Which of the following is a category of organizational process assets?
A. Government standards
B. Organizational culture
C. Employee capabilities
D. Organizational knowledge bases
Which is an example of an internal enterprise environmental factor?
A. Market share brand recognition
B. Factory location
C. Local government regulation
D. Industry research
Which are the most important competencies required for a project manager?
A. Leadership, bilingualism, experience, and technical knowledge
B. PMP certification, experience, technical knowledge, and post-graduate education
C. Leadership, strategic and business management, project management knowledge, and technical knowledge
D. Communication skills, project management knowledge, PMP certification, and availability to travel
A project manager is considering whether or not to procure a new vendor. What can the project manager use to determine a make-or-buy decision?
A. Data analysis
B. Interpersonal skills
C. Bidder conferences
D. Bid documents
Which tools and techniques should a project manager use to monitor risks?
A. Expert judgment, data analysis, and interpersonal and team skills
B. Data analysis, audits, and meetings
C. Expert judgment, audits, and decision making
D. Meetings, data gathering, and expert judgment
In a project using agile methodology, who may perform the quality control activities?
A. A group of quality experts at specific times during the project
B. The project manager only
C. All team members throughout the project life cycle
D. Selected stakeholders at specific times during the project
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
A. Technical project management skills
B. Time management skills
C. Strategic and business management skills
D. Leadership skills
How is the Project Scope Management process different in agile and adaptive projects than in traditional projects?
A. Less time spent on defining scope early on
B. More time spent on defining scope early on
C. Less time spent on scope management process
D. Project scope management is the same in all projects
After defining activities in project schedule management, which processes should a project manager follow?
A. Sequence Activities and Estimate Activity Durations
B. Estimate Activity Durations and Control Schedule
C. Develop Schedule and Control Schedule
D. Review Activities and Develop Schedule
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.