Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :Apr 11, 2025

PMI PMI Certifications CAPM Questions & Answers

  • Question 381:

    Which tool or technique is used to develop a project charter?

    A. Project manager information systems

    B. Expert judgment

    C. Change control meetings

    D. Brainstorming

  • Question 382:

    Which tool or technique measures performance of the project as it moves from project initiation through project closure?

    A. Resource leveling

    B. Parametric measuring

    C. Pareto chart

    D. Earned value

  • Question 383:

    Which of the following methods is a project selection technique?

    A. Flowcharting

    B. Earned value

    C. Cost-benefit analysis

    D. Pareto analysis

  • Question 384:

    Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

    A. Earned value performance

    B. Trend analysis

    C. Cost-benefit analysis

    D. Variance analysis

  • Question 385:

    Which of the following processes are within the Initiating Process Group?

    A. Develop Project Management Plan and Identify Stakeholders

    B. Develop Project Management Plan and Plan Communications

    C. Develop Project Charter and Identify Stakeholders

    D. Develop Project Charter and Develop Project Scope Statement

  • Question 386:

    Which of the following is the correct network diagram for the table?

    A. Begin-A-C-D-E-End-B-D

    B. Begin-A-B-C-D-E-End

    C. Begin-A-B-D-E-End A-C-D

    D. Begin-A-C-D-E-End-B-C

  • Question 387:

    Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?

    A. Estimate Activity Durations

    B. Sequence Activities

    C. Define Activities

    D. Activity Attributes

  • Question 388:

    Which of the following is an example of contract administration?

    A. Negotiating the contract

    B. Authorizing contractor work

    C. Developing the statement of work

    D. Establishing evaluation criteria

  • Question 389:

    Which of the following is an example of push communication?

    A. Intranet sites

    B. Video conferencing

    C. Knowledge repositories

    D. Press releases

  • Question 390:

    Which of the following is an input into the Develop Project Team process?

    A. Enterprise environmental factors

    B. Organizational process assets

    C. Project staff assignments

    D. Performance reports

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.