Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :Apr 19, 2025

PMI PMI Certifications CAPM Questions & Answers

  • Question 661:

    The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

    A. Transfer

    B. Share

    C. Avoid

    D. Accept

  • Question 662:

    The precedence diagramming method (PDM) is also known as:

    A. Arrow Diagram.

    B. Critical Path Methodology (CPM).

    C. Activity-On-Node (AON).

    D. schedule network diagram.

  • Question 663:

    Change request status updates are an output of which process?

    A. Perform Integrated Change Control

    B. Direct and Manage Project Execution

    C. Close Project or Phase

    D. Monitor and Control Project Work

  • Question 664:

    A tool or technique in Perform Quality Control that a project manager would use is:

    A. quality audits.

    B. process analysis.

    C. benchmarking.

    D. inspection.

  • Question 665:

    In which Process Group are lessons learned documented?

    A. Planning

    B. Closing

    C. Executing

    D. Initiating

  • Question 666:

    Tools and techniques used for Plan Communications include the communication:

    A. requirements analysis, communication technology, communication models, and communication methods.

    B. methods, stakeholder register, communication technology, and communication models.

    C. requirements, communication technology, communication requirements analysis, and communication methods.

    D. management plan, communication technology, communication models, and communication requirements analysis.

  • Question 667:

    In Project Cost Management, which input is exclusive to the Determine Budget process?

    A. Scope baseline

    B. Organizational process assets

    C. Project schedule

    D. Resource calendars

  • Question 668:

    Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

    A. Compromising

    B. Collaborating

    C. Smoothing

    D. Problem Solving

  • Question 669:

    Which of the following strategic considerations often results in project authorization?

    A. Customer requests and/or issue resolution

    B. Stakeholder expectations and/or strategic opportunity (business need)

    C. Technological advancement and/or senior executive request

    D. Market demand and/or legal requirements

  • Question 670:

    Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

    A. Limited

    B. Low to moderate

    C. Moderate to high

    D. High to almost total

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.