When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
A. divided among each of the phases or subprojects.
B. repeated for each of the phases or subprojects.
C. linked to specific phases or subprojects.
D. integrated for specific phases or subprojects.
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
A. US$5000
B. US$9500
C. US$10,000
D. US$12,500
The purpose of inspection in Perform Quality Control is to keep errors:
A. in line with a measured degree of conformity.
B. out of the hands of the customer.
C. in a specified range of acceptable results.
D. out of the process.
An input to the Perform Quantitative Risk Analysis process is the:
A. quality management plan.
B. project management plan.
C. communications management plan.
D. schedule management plan.
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
A. enterprise environmental factors
B. organizational process assets
C. project management plan
D. project funding requirements
The milestone list is an input to which process from the Planning Process Group?
A. Define Activities
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities
Quality metrics are an output of which process?
A. Plan Quality Management
B. Perform Quality Control
C. Perform Quality Assurance
D. Perform Qualitative Risk Analysis
A tool and technique used during the Perform Qualitative Risk Analysis process is:
A. risk data quality assessment.
B. variance and trend analysis.
C. data gathering and representation techniques.
D. risk audits.
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
A. Control Schedule.
B. Quality Control.
C. Perform Integrated Change Control.
D. Develop Schedule.
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
A. updates.
B. defect repairs.
C. preventive actions.
D. corrective actions.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.