What is the primary purpose of Project Scope Management?
A. Determining and managing stakeholder needs.
B. Controlling the status of the product scope and managing changes to its baseline.
C. Defining and controlling what is and is not included in the project.
D. Differentiating between the product scope and project scope.
What is the primary benefit of the Manage Quality process?
A. Increases the probability of meeting quality objectives
B. Enhances the performance of the product being created
C. Defines quality roles and responsibilities
D. Ensures that the project is completed as originally planned
What characteristic of servant leadership supports resource management in an agile environment?
A. Lecturing
B. Controlling
C. Measuring
D. Coaching
What three strategies are used to respond to threats?
A. Escalate, accept, and mitigate
B. Accept, share, and avoid
C. Escalate, transfer, and exploit
D. Mitigate, accept, and prioritize
Which is an example of a technical project management skill?
A. Managing a project schedule
B. Developing a project delivery strategy
C. Establishing a project team
D. Understanding organizational objectives
What major skill sets comprise the PMI Talent Triangle?
A. Technical project management, technology management, and strategic and business management
B. Technical project management, leadership, and strategic and business management
C. Leadership, operational management, and technical project management
D. Organizational management, operational management, and technology management
What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?
A. Project Cost Management
B. Project Integration Management
C. Project Risk Management
D. Project Schedule Management
What key component of the project charter defines the conditions for closing a project phase?
A. Purpose
B. Approval requires
C. Exit criteria
D. High-level requirements
What is an example of an emerging trend in procurement management?
A. Online technologies enable projects to postpone ordering long lead items until the items are needed.
B. Online technologies allow a project's progress to be viewed by all stakeholders to build better relations.
C. Online procurement tools provide buyers with multiple sources to advertise to sellers.
D. Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.
What is the main benefit of the lessons learned register?
A. Provides validation requirements
B. Supplies monitoring and reporting methods
C. Improves the performance of future projects
D. Documents the status of deliverables and project results
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.