Which of the following would MOST likely contain warranty information for the project deliverable?
A. Scope statement
B. Cost baseline
C. Risk assessment
D. Transition plan
Which of the following BEST describes the chart of accounts?
A. The numbering system used to monitor the quality measurements during the life of the project.
B. The numbering system used to track project costs depending on their activity type.
C. The numbering system used to decompose project activities into sub-project activities.
D. The numbering system used to identify each activity on the work breakdown structure.
The initial quality measurements used to determine if a variance has occurred is known as the:
A. Quality checklist.
B. Baseline.
C. Quality metrics
D. Control limit.
Which of the following documents would a project manager review to determine all the identified risks on a project?
A. Risk matrix
B. Risk register
C. Risk response
D. Risk baseline
A project manager needs to replace someone on the project team. Which of the following is the FIRST action they should take?
A. Consult the project staffing plan.
B. Notify the human resources department to open a job posting.
C. Search for skilled subcontractors who could quickly fill the opening.
D. Ask the project sponsor for another resource.
A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?
A. ADM
B. WBS
C. AON
D. PDM
A project manager has analyzed work performance information and identified alarming variances in the project deliverable. Which of the following would be the BEST response for the project manager?
A. Perform a qualitative risk assessment.
B. Speak with the project sponsor about possible solutions.
C. Approve a change request to correct the actions.
D. Recommend corrective actions.
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
A. Obtain additional approval from the project sponsor.
B. Discuss this change during the next status meeting.
C. Perform a probability and impact analysis on the change.
D. Create a plan to implement the change.
The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?
A. Discuss this change during the next status meeting.
B. Ask other stakeholders for recommendations.
C. Send the request to the change control board.
D. Perform an impact analysis.
A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?
A. Stakeholder analysis
B. Risk assessment
C. Audit review
D. Phase gate
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.