  • Question 121:

    A project manager wants to have complete control of the project team members. Which of the following organization structures would allow for this?

    A. Functional

    B. Balanced matrix

    C. Strong matrix

    D. Projectized

  • Question 122:

    Faced with a complex project with many stages, which of the following is the BEST action for the project manager to take?

    A. Employ phase closure meetings.

    B. Encourage vendors to work overtime.

    C. Request a schedule extension.

    D. Hire additional contractors.

  • Question 123:

    Which of the following occurs during administrative closure?

    A. Requiring input from the sponsor on the project objectives.

    B. Updating quality expectations for the deliverables.

    C. Closing out contracts with vendors.

    D. Revealing new WBS tasks to team members.

  • Question 124:

    When would a project manager have a closure meeting? (Select Three).

    A. Stage completion

    B. Task completion

    C. Document completion

    D. Project cancellation

    E. Project completion

    F. Vendor cancellation

  • Question 125:

    Which of the following would be the benefit of saving a project binder in a centralized location?

    A. Provides an opportunity for another project manager to review the binder and make corrections.

    B. Provides an opportunity for team members to review their contributions.

    C. Provides other project managers the opportunity to review the project information.

    D. Provides stakeholders the opportunity to modify the change request forms.

  • Question 126:

    It is important to complete a formal project closure process to: (Select Three).

    A. assure that the customer will work with all vendors in the future.

    B. confirm that the stated project objectives were met.

    C. confirm that the customer accepts the final deliverables.

    D. collect new information to enter into the issue log for further review.

    E. assure that the contract is complete and the team members can be released.

    F. collect additional scope requirements that need to be entered into the project plan.

  • Question 127:

    When a project ends unexpectedly, which of the following should the project manager do?

    A. Create an end document to add to the file before moving on to another project.

    B. Create a document identifying the negative impact of the early project ending to give to the customers management.

    C. Perform project close out with full documentation and review.

    D. Perform a limited project close that consists of releasing team members.

  • Question 128:

    Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).

    A. It determines the project milestones.

    B. It determines the project budget.

    C. It outlines the communication plan for the team.

    D. It determines the resources required to complete project tasks.

    E. It outlines the statement of work (SOW) for the project.

  • Question 129:

    If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

    A. -$1,000

    B. $1,000

    C. -$3,000

    D. $3,000

    E. There would be a 25 percent cost decrease.

    F. There would be a 75 percent cost increase.

    G. The project is over-budget.

    H. The project is under-budget.

  • Question 130:

    Which of the following would be the impact upon a project if the CPI for the project is .75?

    A. The project is under-budget.

    B. There would be a 25 percent cost decrease.

    C. There would be a 75 percent cost increase.

    D. The project is over-budget.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.