During a status meeting, a team member informs the project manager of a possible risk. Which of the following is the FIRST action the project manager should take?
A. Record the risk in the risk register.
B. Work with the team to develop a risk response.
C. Perform an initial prioritization of the risk.
D. Determine the probability and impact of the risk.
A project manager has decided to reduce the impact of a possible threat. Which of the following risk response strategies BEST describes this action?
A. Avoidance
B. Exploiting
C. Mitigation
D. Acceptance
Quality assurance is performed during which phase of a project?
A. During the controlling phase
B. During both controlling and execution phase
C. During the execution phase
D. During the planning phase
A project manager was called into the office of the Chief Information Officer (CIO) and informed that the
resource budget for the company has been reduced by 10%. The CIO expects that the project must be
completed on time.
Which of the following will be impacted?
A. Project scope will be impacted.
B. Quality will be impacted.
C. WBS will be impacted.
D. SOW will be impacted.
Which of the following should a project manger do to actively track issues as they are identified?
A. Develop a quality management plan.
B. Create a process for anonymous team review of issue resolution.
C. Make an issues log template.
D. Update the issues log.
Which of the following can the project manager do to manage scope creep?
A. Be open minded to new ideas to the project.
B. Be flexible about what needs to be done to complete the project.
C. Be specific when defining project objectives in the project plan.
D. Be positive when approached with changes to ensure customer satisfaction.
Which of the following documents should be used to present the length of identified tasks?
A. CPM
B. Key event/activity list
C. PERT
D. Gantt
Before a change request is presented to the change control board, which of the following should the project manager do?
A. Suggest the board study the cost of the change.
B. Evaluate the affect on all other parts of the project.
C. Review the change request with the project sponsor.
D. Request team member input on the value of the change.
Which of the following is the BEST definition of a stakeholder? (Select Two).
A. Anyone impacted negatively by the project.
B. Anyone who is in the company where the project is taking place.
C. Anyone who is interested in the project.
D. Anyone who negatively impacts the project.
E. Anyone impacted positively by the project.
Which of the following would be contained in the problem statement within the project charter?
A. The issues that might block a vendor's success.
B. The conflict between management and the project vendors.
C. The issues the customer wants resolved.
D. The conflict management style that will be used during the project.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.