CompTIA CompTIA Project+ PK1-003 Questions & Answers

  • Question 201:

    Which of the following may include meetings, status reports, and email distribution lists?

    A. Change control plan

    B. Meeting minutes

    C. Project schedule

    D. Communication plan

  • Question 202:

    A project team has determined that all status reports will be sent via email. Which of the following components of the project plan documents this information?

    A. Status report plan

    B. Communication plan

    C. Discussion plan

    D. Decision log

  • Question 203:

    Which of the following project documents lists risks and describes the strategy to deal with a risk?

    A. Risk categorization

    B. Risk register

    C. Risk analysis

    D. Risk breakdown structure

  • Question 204:

    Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group?

    A. Avoiding

    B. Smoothing

    C. Forcing

    D. Compromising

  • Question 205:

    Which of the following techniques modifies the schedule based upon resource constraints?

    A. Critical Chain Method

    B. Critical Path Method

    C. Arrow Diagramming Method

    D. Precedence Diagramming Method

  • Question 206:

    Resources for a project report to a project manager and a functional manager. The organizational structure is:

    A. Matrix

    B. Ad hoc

    C. Functional

    D. Projectized

  • Question 207:

    Which of the following conflict resolution techniques focuses on a positive relationship and deemphasizes the area of conflict?

    A. Avoiding

    B. Smoothing

    C. Compromising

    D. Forcing

  • Question 208:

    Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

    A. Critical Path Method

    B. Arrow Diagramming Method

    C. Critical Chain Method

    D. Precedence Diagramming Method

  • Question 209:

    Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

    A. Critical Path Method

    B. Critical Chain Method

    C. Arrow Diagramming Method

    D. Gantt Chart Method

  • Question 210:

    The project's network map has a loop with multiple project outcomes. This is the result of which of the following scheduling tools?

    A. Establishing project schedule baselines

    B. Critical Path Analysis

    C. Critical Chain Method

    D. Graphical evaluation and review technique

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.