Exam Details

  • Exam Code
    :PK1-003
  • Exam Name
    :CompTIA Project+ Beta Exam
  • Certification
    :CompTIA Project+
  • Vendor
    :CompTIA
  • Total Questions
    :320 Q&As
  • Last Updated
    :Apr 08, 2025

CompTIA CompTIA Project+ PK1-003 Questions & Answers

  • Question 211:

    Which of the following tools would a project manager use to determine the root cause of an issue?

    A. Pareto Chart

    B. Ishikawa Diagram

    C. Histogram

    D. Monte Carlo Analysis

  • Question 212:

    The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:

    A. Transference

    B. Sharing

    C. Avoidance

    D. Acceptance

  • Question 213:

    The final project report should contain which of the following?

    A. Minutes of all the project meetings

    B. Project design documentation

    C. Detailed breakdown of the schedule

    D. Summary of the project cost

  • Question 214:

    Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

    A. Managing change

    B. Fast tracking

    C. Rolling wave planning

    D. Crashing

  • Question 215:

    A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Select TWO).

    A. Lessons learned during the project

    B. Produce operational support documentation

    C. Gathering and centralizing project documentation

    D. Organizing the communication of project closure

    E. Identify the key project achievements

    F. Provide a recap of the overall solution

  • Question 216:

    Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should the project manager do to ensure stakeholder expectations are met?

    A. Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps

    B. Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks

    C. Escalate the issue to the project steering committee that Ann is criticizing the project quality

    D. Organize a requirements workshop to capture any gaps

  • Question 217:

    A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on: A. Prioritizing the specific event.

    B. Variance in the process over time.

    C. Causes of a specific event.

    D. Determining the number of events.

  • Question 218:

    The design activity of a project has the following cost attributes:

    PV = 100,000

    EV = 20,000

    AC = 90,000

    Based on this scenario, calculate the schedule variance.

    A. -80,000

    B. -70,000

    C. 10,000

    D. 120,000

  • Question 219:

    The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

    A. Cost performance index

    B. Risk mitigation

    C. Schedule variance

    D. Cost variance

  • Question 220:

    The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager?

    A. Rescheduling

    B. Crashing

    C. Rebaselining

    D. Control scope

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.