When an Agile project team receives an "emergency request" during an iteration, which is the best first step that the Agile project manager should take?
A. Stop work on unfinished user stories and work on the urgent request.
B. Call a team meeting and change the iteration scope to include the request.
C. Provide the customer with options provided by the project team.
D. Explain that the team cannot do the added work until the next iteration.
Agile project development processes typically:
A. Encapsulate analysis, design, code, and test within an iteration.
B. Document each business process individually and in detail.
C. Use a Gantt chart with well-defined activities, responsibilities, and time frames.
D. Map the iteration backlog to a Work Breakdown Structure (WBS).
Which of the following is an example of a visual aid used in Lean-Agile software development?
A. Business value delivered chart
B. Product technical specifications
C. Automated code coverage report
D. Scrum-of-Scrum report
What is the best description of the relationship between Scrum and extremeProgramming(XP)?
A. XP is a component of Scrum.
B. The principles of each are often complementary.
C. Scrum is a component of XP.
D. The principles of each are often contradictory.
Who is responsible for prioritizing the stories that will be included in the iteration?
A. ScrumMaster
B. Developer
C. Product Owner
D. Team
On a project using eXtreme Programming (XP), a customer test is a:
A. Technique to determine if the software is easy for customer use.
B. Tool for a customer to verify the business requirements.
C. Technique to determine if a customer will use a software feature.
D. Test for determining if a customer will purchase the product.
Team A is producing 61 points per iteration and Team B is producing 20 points per iteration. Team A has more senior engineers. A manager demands that Team B match Team A's points in the next iteration. Based on this information, it is reasonable to tell the manager that:
A. it is impossible to compare two separate teams on points alone.
B. Team B's points will match Team A if Team B gets more senior engineers.
C. Team B must have help self-organizing so their points match Team A.
D. Team B's points will increase if the Product Owner becomes more involved.
Which of the following is a list of valid Agile project planning practices?
A. Release planning, Iteration planning, and Estimation
B. Estimation, Spike Solutions, and Iteration planning
C. Iteration planning, Continuous Integration, and Estimation
D. Vision, Release planning, and Performance Optimization
Which best describes the attributes of the IN VEST criteria in a user story?
A. Incremental, Net, Variation, Exceed, Scope, and Training
B. Interdependent, Nonfunctional, Value, Exploratory, Sprint, and Timebox
C. Innovation, Nested, Vision, Estimating, Scalable, and Team
D. Independent, Negotiable, Valuable, Estimable, Small, and Testable
A user story says that a product must be very fast. During the demo, the Product Owner is dissatisfied with the speed of the product. The most likely reason that this occurred is because the user story was:
A. Too large.
B. Not estimated correctly.
C. Not testable.
D. Not descriptive of the value.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.