Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Apr 04, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 481:

    A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

    What should the project manager do next?

    A. Update the project management plan to add contingency.

    B. Perform an assumptions and constraints analysis.

    C. Complete an assessment and confirm the response with the sponsors.

    D. Implement mitigation measures for those risks.

  • Question 482:

    During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

    How should the risk manager handle this situation?

    A. Request for a skilled facilitator to help resolve conflicts that have arise.

    B. Refer to the team's ground rules on how to resolve conflicts.

    C. Run a sensitivity analysis to check which risks have the most impact.

    D. Use the assumption analysis techniques to validate the assumptions.

  • Question 483:

    The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

    What should the project manager do regarding those risks?

    A. Review the assumptions analysts

    B. Conduct a checklist analysis on each risk

    C. Create a risk response plan for those risks

    D. Review the risk register to check for the new risks

  • Question 484:

    Which statement describes the risk portrayed on the risk matrix heat map below?

    A. The risk has a probability of 60% of occurrence and a medium impact rating.

    B. The risk has a probability of 40% of occurrence and a high impact rating.

    C. The risk has a high impact and probability of occurring.

    D. The risk has a low probability and high impact rating.

  • Question 485:

    The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

    What should the project manager do?

    A. Wait until the weather improves before sending the equipment.

    B. Ask the project sponsor to approve shipping the equipment.

    C. Proceed with the planned risk response to move the equipment.

    D. Request the shipment of the equipment to satisfy the client.

  • Question 486:

    A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

    A. Highlight this situation to the project manager

    B. Conduct a cost-benefit analysis

    C. Change the risk response strategy

    D. Analyze the situation and meet with the risk owner

  • Question 487:

    The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

    A. Use the Delphi technique involving experts who have identified opportunities in the past

    B. Interview more stakeholders who have a positive mindset

    C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

    D. Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

  • Question 488:

    When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

    What should the project manager do?

    A. Process the freight invoices at higher shipping costs against the project's contingency allowance.

    B. Request a formal change order from the customer to increase the project's total budget.

    C. Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

    D. Ask the project sponsor to cover the additional shipping costs on the company's reserves account.

  • Question 489:

    A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

    What should the risk manager complete first?

    A. The risk categorization

    B. The risk simulation

    C. The full risk description

    D. The risk response plan

  • Question 490:

    An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.

    What should the risk management team leader do in the early stages of the project?

    A. Conduct qualitative risk analysis to prioritize potential risks.

    B. Plan a solid risk response plan and secure the necessary funding.

    C. Educate stakeholders on best practices to perform risk management.

    D. Benchmark to an organization which has executed a similar project,

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.