Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 491:

    A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

    What should the risk manager do?

    A. Import a risk register from other industry chemical laboratories.

    B. Define chemical laboratory safety risk thresholds.

    C. Review published operational experience reports.

    D. Draft threat and opportunity risks that come to mind.

  • Question 492:

    Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

    A. The risk management plan

    B. The risk triggers

    C. The risk prioritization criteria

    D. The portfolio management plan

  • Question 493:

    A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

    What two actions should the risk owner take? (Choose two.)

    A. Implement the secondary risk response and update the project documents.

    B. Conduct meeting with all stakeholder to agree on post impact solutions.

    C. Set the corresponding trigger conditions to the secondary risk.

    D. Engage the project manager to authorize the secondary risk's response.

    E. Update and communicate assessments of the secondary risk's impact.

  • Question 494:

    The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

    How should this documentation be utilized in the future?

    A. To return the remaining amount of the contingency reserve

    B. To ensure information is recorded for lessons learned

    C. To comply with the rules and regulations

    D. To hold those who created the risk accountable

  • Question 495:

    The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

    What should the project risk manager do next to identify risks?

    A. Review the risk breakdown structure to ensure project scope is covered.

    B. Use the brainstorming technique to remove personal bias.

    C. Use expert judgment to remove ego or emotional conflict.

    D. Consider the Delphi technique to gather all stakeholder opinions.

  • Question 496:

    A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

    A. Review potential next steps with the project team.

    B. Review the scope of work to determine the prescribed project methodology.

    C. Review the policies and practices that are outlined in the risk management plan.

    D. Review the contract and determine the resources and project funding.

  • Question 497:

    The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

    What recommendation should the risk manager make to the project manager?

    A. Add more float to the key activity

    B. Add more contingency to the project

    C. Review the plans for the key activity

    D. Increase the budget for the key activity

  • Question 498:

    The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks. What are two options the risk manager should consult for the analysis? (Choose two.)

    A. Proximity dales for open risks

    B. Backlog of change orders to be submitted to client

    C. Risks that have materialized and the overall risk profile

    D. Number of schedule baseline changes approved

    E. Risks due to the number of claims submitted to the client

  • Question 499:

    A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

    A. Risk mitigation

    B. Risk transfer

    C. Risk acceptance

    D. Risk avoidance

  • Question 500:

    A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

    Which data analysis tool should the risk manager use to forecast future performance?

    A. Sensitivity analysis

    B. What-if scenario analysis

    C. Regression analysis

    D. Decision tree analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.