Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 501:

    A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

    What should the risk manager do?

    A. Ask the project sponsor if every risk in the risk register can have the same priority.

    B. Mark every identified risk as an extremely high priority and any future risks as a lower priority.

    C. Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

    D. Perform a sensitivity analysis and determine the correct priority of every identified risk.

  • Question 502:

    When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

    A. Request a contingency reserve from management

    B. Arrange a team meeting, review the project's scope, and discuss dependency mapping

    C. Ensure participants review relevant documents before attending the meeting

    D. Ensure that all the relevant stakeholders participate

    E. Update the risk register during the team meeting.

  • Question 503:

    A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

    What should the project manager do next to determine risk impact of assumptions and constraints?

    A. Add all assumptions and constraints to the risk register.

    B. Add the risk impact of the assumptions in the risk register.

    C. Add the assumptions and constraints to the assumption log.

    D. Add the assumptions and constraints in the project charter.

  • Question 504:

    A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

    A. Include all stakeholders in the project's governance.

    B. Communicate response strategies to all stakeholders.

    C. Ignore any risks beyond stakeholders' tolerance.

    D. Consider stakeholders' positions and opinions regarding the project's output.

  • Question 505:

    A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

    What should the risk manager of the related project have done to prevent this situation from happening?

    A. Reformed the risk monitoring and closing process properly.

    B. Created the project work plan and budget more accurately.

    C. Educated the project team on budget change requests.

    D. Communicated better with the organization's CEO.

  • Question 506:

    In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

    What should the risk manager do?

    A. Update the risk register accordingly and review it in regular project meetings.

    B. Accept the risk because residual risks are often low.

    C. Ask a subject matter expert (SME) to assess the residual risk and take action.

    D. Assign a risk owner and set it as high priority and high impact.

  • Question 507:

    A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

    What is the expected outcome of developing the risk management plan?

    A. Being able to monitor and control risks throughout the project.

    B. Defining how risk management will be executed throughout the project.

    C. Documenting the communication strategy for risks throughout the project.

    D. Having the ability to identify risks throughout the project.

  • Question 508:

    During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

    A. A potential need to share the space with other machinery

    B. A different type of equipment received before installation

    C. A time delay during air conditioning installation activities

    D. A quality nonconformance issue raised during the inspection

  • Question 509:

    A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

    What should the risk manager do next with the data set?

    A. Perform a probability and impact assessment

    B. Perform Monte Carlo simulations

    C. Perform a sensitivity analysis

    D. Perform a risk data quality assessment

  • Question 510:

    The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

    What is this an example of?

    A. Risk responses

    B. Risk triggers

    C. Risk registers

    D. Risk categories

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.