Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 511:

    An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

    What should the risk manager do next?

    A. Add only the threats to the risk register

    B. Utilize different tools to identify the risks

    C. Plan risk responses to the threats

    D. Update the risk register with the identified risks

  • Question 512:

    The project manager performed' a variance analysis on the project during the execution phase. The variances were shown as increasing

    What does this result imply?

    A. The uncertainty and risk are increasing.

    B. The project schedule is lagging behind.

    C. There is no potential for future deviation.

    D. The project is over budget.

  • Question 513:

    The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

    What should the project manager do first?

    A. Include the risk in the register and communicate with the stakeholders.

    B. Communicate with the client to provide the previous shutdown plan.

    C. Review and update the project schedule.

    D. Interview the other project manager to learn more details.

  • Question 514:

    A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

    Which kind of numerical analysis should be performed to understand the worst-case scenarios?

    A. Earned value analysis

    B. Qualitative risk analysis

    C. Sensitivity analysis

    D. Root cause analysis

  • Question 515:

    During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

    A. Strengths, weakness, opportunities, and threats (SWOT) analysis

    B. Delphi technique

    C. Decision tree analysis

    D. Probability impact matrix

  • Question 516:

    A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

    How should the project manager handle stakeholder expectations?

    A. Add buffers to the schedule to accommodate risk.

    B. Ensure the risk register includes all identified risks.

    C. Discuss the risk response strategies with the stakeholders.

    D. Develop a communication plan to share updates on risks.

  • Question 517:

    When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

    A. Select the strategies with the least overall impact to resources.

    B. Select the strategies with the least financial impact.

    C. Select the strategies with the greatest overall positive influence.

    D. Select the strategies with the greatest benefit to stakeholders.

  • Question 518:

    A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

    What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

    A. Scope of work and requirements

    B. Monte Carlo analysis from a similar project

    C. List of pre-approved contractors

    D. Organization chart for city permit department

    E. Risk management plan

  • Question 519:

    A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

    How should a professional risk manager manage the risks in such situations?

    A. Adopt a predictive approach to manage the risks.

    B. Adopt agile approaches to manage the risks.

    C. Utilize proper documentation to help manage the risks.

    D. Conduct weekly risk management meetings with all stakeholders.

  • Question 520:

    After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

    What should the risk manager do to facilitate the sponsor's ask?

    A. Monte Carlo analysis

    B. Qualitative risk analysis

    C. Sensitivity analysis

    D. Quantitative risk analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.