Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 521:

    During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

    What should the risk manager do first?

    A. Update the new risk in the risk register.

    B. Plan responses for the new risk.

    C. Passively accept the new risk.

    D. Add the new risk to the watch list.

  • Question 522:

    A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

    How should the project manager work with these risk handling strategies?

    A. Review and revise the strategies periodically.

    B. Implement the strategies after completing the risk analysis.

    C. Implement the strategies immediately.

    D. Ensure the strategies are approved by the stakeholders.

  • Question 523:

    Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

    A. When the forecast activity date has been met or exceeded

    B. When the stakeholders agree a risk is no longer applicable

    C. When the risk has been realized and can no longer happen again

    D. When iterative data analysis determines the risk is not applicable

  • Question 524:

    A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

    What should the project manager have done to avoid this?

    A. Provided regular training to the risk owners for plan implementation

    B. Determined risk triggers and thresholds in the risk response plan

    C. Increased communications to influence stakeholder risk responses

    D. Updated the project schedule, adding risk owner implementation tasks.

  • Question 525:

    A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

    Where should the project manager find this information?

    A. Industrial studies

    B. Commercial risk databases

    C. Organizational process assets (OPAs)

    D. Enterprise environmental factors (EEFs)

  • Question 526:

    What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

    A. Organizational communication requirements

    B. Organizational standard policies, processes, and procedures

    C. Formal knowledge sharing and information sharing procedures

    D. Confidentiality of project information

  • Question 527:

    A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

    Which document will need to be updated?

    A. Lessons learned

    B. Contingency register

    C. Risk register

    D. Issue log

  • Question 528:

    A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

    What should the risk manager do with this risk?

    A. Put the risk on the watch list.

    B. Seek guidance from subject matter experts (SMEs).

    C. Ignore this risk as it is not critical.

    D. Inform the stakeholders about this risk.

  • Question 529:

    A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

    What should the risk manager do next to visually organize the risks?

    A. Develop an affinity diagram

    B. Perform the analytical hierarchy process

    C. Perform a SWOT analysis

    D. Assign probability and impact

  • Question 530:

    Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

    What should the risk manager do to avoid the previous issues?

    A. Use the information for a risk workshop.

    B. Improve monitoring and controlling of activities.

    C. Document the issues in the lessons learned.

    D. Create an issue log to share with the team.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.