Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 541:

    A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

    Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3) A. Verify whether or not any identified risks might occur and implement the risk response plan.

    B. Regularly check and report on the status of risks identified according to their prioritization.

    C. Monitor the status and oversee execution of the risk response plan for each identified risk.

    D. Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

    E. Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

  • Question 542:

    Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

    A. Exclude risk averse stakeholders from future risk discussions

    B. Explain risk handling and mitigation strategies

    C. Increase the impact of all risks in the risk breakdown structure (RBS)

    D. Develop a generous probabilistic cash flow model

  • Question 543:

    While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

    A. Issue log

    B. Change log

    C. Assumption log

    D. Risk-adjusted back log

  • Question 544:

    The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

    A. Update the assumptions/exclusions register

    B. Hire more resources and crash the schedule

    C. Perform a qualitative risk analysis for the project

    D. Mitigate risks identified on the sensitivity analysis

  • Question 545:

    In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

    How should the project manager address this concern with the health authorities?

    A. Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

    B. Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

    C. Assess and record associated secondary risks and proceed to treat them as any other risks.

    D. Proceed with the project as normal since a minor number of residents will be effected negatively.

  • Question 546:

    A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

    What should the project manager do to evaluate and select the best option based on costs and probabilities?

    A. Perform a FMECA fault tree analysis

    B. Conduct a sensitivity analysis

    C. Perform a decision tree analysis

    D. Conduct an analytic hierarchy process

  • Question 547:

    At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

    How should the project manager handle this situation?

    A. Outsource conducting the risk response plan to risk consultants.

    B. Ask functional managers to improve their risk register and process.

    C. Adjust the risk response plans to effectively handle the identified risks.

    D. Coach the functional groups on how to properly conduct the process.

  • Question 548:

    In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about to drop their intention to continue executing the project. The risk manager does not understand their decision.

    What should the risk manager do next to understand the major stakeholder's decision regarding the project?

    A. Perform a risk impact analysis.

    B. Perform a risk reserve analysis.

    C. Perform a procurement analysis.

    D. Perform a stakeholder impact and influence analysis.

  • Question 549:

    During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

    A. Utilize a Monte Carlo assessment to provide risk related impacts.

    B. React to the secondary and residual risks only if they occur.

    C. Include secondary and residual risks as part of the response.

    D. Transfer secondary and residual risks to the project sponsor.

  • Question 550:

    An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

    What should the risk manager do next?

    A. Assess the identified secondary risk.

    B. Implement the risk response plan.

    C. Implement the risk contingency plan.

    D. Communicate the identified residual risk.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.