Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 551:

    While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

    What should the project manager do next?

    A. Identify secondary or residual risks for associated risk plans.

    B. Develop risk response plans for all identified risks.

    C. Update the communications management plan to avoid future issues

    D. Monitor and control secondary and residual risks in the risk register.

  • Question 552:

    Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

    What should the project manager do next?

    A. Review assumptions and constraints around risks.

    B. Develop the risk response plans for identified risks.

    C. Determine the likelihood and impact of the risks.

    D. Apply an iterative approach to risk identification.

  • Question 553:

    A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

    A. Each cause has a degree of uncertainty

    B. Each cause has well defined owner

    C. The causes represent actual conditions

    D. The causes must be validated by the risk owner

  • Question 554:

    A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

    What is an effect of adding the correlation to the model?

    A. Allows more risks to be included in the model.

    B. Reduces the project completion duration.

    C. Increases the standard deviation of the model.

    D. Increases the probability of correlated activities finishing on time.

  • Question 555:

    A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the client's vendor, which apparently has been causing all of the issues.

    What should the risk manager do first?

    A. Enhance risk identification.

    B. Review the contingency reserves.

    C. Create a risk response plan.

    D. Review the risk registry.

  • Question 556:

    A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

    A. US$20.000 loss

    B. US$20,000 profit

    C. US$40,000 loss

    D. US$100,000 profit

  • Question 557:

    During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

    A. Contact the risk managers of the other projects and inform them

    B. Include an escalation process in the risk management plan

    C. Take note of the extensive impact of these risks in the risk register

    D. Address the unique characteristics of these risks on a case-by-case basis

  • Question 558:

    A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

    A. Identify risks only at the project's midpoint for the stakeholders to review them

    B. Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

    C. Identify risks at the beginning of the project because the risk posture will not change

    D. Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

  • Question 559:

    A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

    Which risk identification technique should the risk manager use?

    A. Prompt lists

    B. Interviews

    C. Delphi technique

    D. Nominal group technique

  • Question 560:

    A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

    A. Risk management plan

    B. Clients' credit scores

    C. Organization's mission and vision

    D. Historical data from the credit portfolio

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.