Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 16, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 191:

    You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?

    A. +110

    B. -25

    C. -110

    D. +25

  • Question 192:

    You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?

    A. Project schedule

    B. Work performance information

    C. Project management plan

    D. Earned value management results

  • Question 193:

    You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

    A. Decomposition

    B. Rolling wave plan

    C. Precedence diagramming method

    D. Templates

  • Question 194:

    You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?

    A. Crashing increases project costs.

    B. Crashing is a top-down approach to project completion.

    C. Crashing restricts resource utilization.

    D. Crashing always increases project risks.

  • Question 195:

    Examine the figure given below:

    You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailability of the resources from the vendor. What will this delay do to your project completion, if you allow the delay to enter into the project?

    A. The project will be one day late.

    B. The float for activity D will be consumed.

    C. The project can still finish on time.

    D. The project will be seven days late.

  • Question 196:

    Which of the following is an output of the Identify Stakeholders process?

    A. Scope baseline

    B. Project scope statement

    C. Project charter

    D. Stakeholder register

  • Question 197:

    Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?

    A. - $210,000

    B. - $720,000

    C. - $250,000

    D. - $270,000

  • Question 198:

    You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

    A. Project scope statement

    B. Milestone list

    C. Project schedule network diagrams

    D. Activity list

  • Question 199:

    Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

    A. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

    B. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

    C. The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

    D. The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

  • Question 200:

    You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus on creating time estimates for the most imminent research work and broad estimates for the project work that is coming later in the project. What type of planning are you using in this project?

    A. Milestone planning

    B. Rolling wave planning

    C. Phase gates

    D. Decomposition

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.