  • Question 241:

    A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?

    A. Analyze the interests and influence of stakeholders and evaluate their requirements.

    B. Include only the key requirements and keep the stakeholders informed about scope decisions.

    C. Add only the opinions of the team, because they know the objectives of the project.

    D. Include only the common requirements of each stakeholder group in the project goals.

  • Question 242:

    A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

    What should the project manager do first?

    A. Register a new risk in the risk management plan.

    B. Review organizational process assets (OPAs) and perform analogous estimating.

    C. Ask for additional resources and review the project estimate.

    D. Complete a bottom-up estimation for the project activities.

  • Question 243:

    A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration. What should the project manager do to lead the project?

    A. Use a servant leader approach.

    B. Act as the project owner.

    C. Perform the project sponsor activities.

    D. Assume the functional manager role.

  • Question 244:

    Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

    What should the project manager do to obtain agreement from both companies and acceptance from marketing?

    A. Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.

    B. Stop the current release work for 4 weeks in order to work and deliver the new feature completely.

    C. Create a special release 4 weeks after the current release to deliver the new feature in its entirety.

    D. Add the new feature to the list for the next release and continue working on the current release.

  • Question 245:

    The deliverables of a project have been completed. However, the stakeholders did not approve the deliverables, because they did not cover the needs of the business. Which actions should the project manager have taken to avoid this situation?

    A. Defined the project management plan and ensured it met the project objectives and business needs.

    B. Ensured that the stakeholders participated in the daily meetings to confirm that the project was developing correctly.

    C. Provided and explained the sprint backlog at the beginning of the project to the stakeholders and project team.

    D. Requested that the team change the frequency of the deliverables in the development phase to obtain earlier feedback.

  • Question 246:

    A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case. What should the project manager do?

    A. Ensure the client representative is involved in the estimation.

    B. Ensure that a 20% contingency is included in the estimation.

    C. Review the completion costs of similar projects.

    D. Review the lessons learned from similar projects.

  • Question 247:

    The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.

    What should the project manager do?

    A. Promote engineer B instead since the project manager has the authority to make this decision.

    B. Help engineer A to become familiar with this new role and ensure engineer B stays motivated.

    C. Coach engineer B to be prepared to perform this role if and when engineer A fails.

    D. Request management approval that engineer B will be promoted if engineer A fails in this role.

  • Question 248:

    Some of the team members who are working on a new software tool are in a public space, arguing over a new feature being coded instead of completing the coding. How should the project manager handle this situation and get the team to complete the task?

    A. Contact the human resources (HR) department to tell them there is an argument in a public space and that they need to intervene immediately.

    B. Engage in the conversation in the public space by telling them the expectations of the feature and advise them to return to their workspace.

    C. Listen to the argument from a nearby location to understand the situation, then offer insight into the features when the team is calm.

    D. Bring the team members to the meeting room to discuss the new feature and to reach a common understanding of the necessary coding.

  • Question 249:

    A project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and the conclusion is that there is not an adequate flow of work for the team. What should the project manager do?

    A. Provide the product owner with training.

    B. Submit a change request to rebaseline the project.

    C. Change the project approach to hybrid.

    D. Discuss the issue with the stakeholders.

  • Question 250:

    A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product.

    What should the project manager do?

    A. Ask the sales team to inform the customer.

    B. Contact the customer's project manager.

    C. Ask the product owner to inform the customer.

    D. Contact the customer's technical lead.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.