Which type of projects needs to consider environmental constraints?
A. Construction projects only.
B. Construction and petrochemical projects only.
C. All but IT projects.
D. All projects.
When managing the internal context, the project manager should especially be aware of:
A. organisational strategy, policies and frameworks.
B. competitive positioning.
C. new legislation.
D. business continuity.
To be fully effective, the project manager:
A. must take into consideration the internal and external environments.
B. need only deal with the internal environment since the sponsor will deal with the external environment.
C. should manage the external stakeholders and external environment.
D. must liaise with regulating bodies to ensure requirements include the latest legislation.
Which of the following best describes a project's context?
A. The environment in which the business operates.
B. The geographic location in which the project is undertaken.
C. The external and internal business environments including stakeholder's interests and influences.
D. Industry and business sector practices.
PESTLE analysis covers the following areas:
A. Political, Economic, Sociological, Technical, Legal, Environmental.
B. Personnel, Economic, Safety, Technical, Legal, Ecological.
C. Political, Ecological, Strategy, Technical, Life cycle, Environmental.
D. Personnel, Ecological, Sociological, Training, Life cycle, Ecological.
Which one of the following is NOT a function of leadership?
A. Reinforcing positive relationships.
B. Inspiring the individual.
C. Maintaining constant tight control.
D. Promoting the project vision.
Good teamwork helps to deliver a successful project because:
A. team members have similar skill sets.
B. project work can be distributed equally around the team.
C. all team members have the same access to project information.
D. people work collaboratively towards a common goal.
A project communication plan identifies the relevant information that should be communicated to:
A. the project team.
B. the project stakeholders.
C. the project board.
D. the project sponsor
The project team comprises:
A. all those responsible to the project manager who are working towards the project objectives.
B. the members of staff who are allocated full time to the project.
C. the members of staff who report to the project manager and who carry out work on the project.
D. all project stakeholders.
Which one of the following statements best describes communication?
A. The giving, receiving, processing and interpretation of information.
B. The explanation, understanding, managing and sorting of information.
C. The giving, explaining, understanding and interpretation of information.
D. The managing, receiving, processing and sorting of information.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.