  • Question 11:

    To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

    A. Process moving

    B. Brainstorming

    C. Interview

    D. Focus group

  • Question 12:

    A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

    A. Scope creep

    B. Collecting requirements

    C. Decision-making

    D. Project change

  • Question 13:

    A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

    A. Removing access

    B. Closing contracts

    C. Project sign-off

    D. Project evaluation

  • Question 14:

    Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

    A. Data security

    B. Operational security

    C. Physical security

    D. Digital security

  • Question 15:

    A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

    A. The vendor's proposed schedule does not align with the desired schedule.

    B. The vendor is new and not well established in the market.

    C. The vendor has been linked to ESG concerns within the past month

    D. The vendor's quote was the highest of all the proposals.

  • Question 16:

    A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

    Which of the following can be formally conducted?

    A. The team member prioritized other tasks over the completion of this task

    B. The learn member had performance issues over time.

    C. There is a negative correlation with time and output

    D. This is a display of units of outstanding work to predict completion

  • Question 17:

    A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

    A. List both positively and negatively impacted stakeholders.

    B. Update the communication plan with the new findings.

    C. List the negatively impacted stakeholders only.

    D. List the positively impacted stakeholders only.

  • Question 18:

    A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

    A. Demonstration

    B. Workshop

    C. Brainstorming

    D. Focus group

  • Question 19:

    Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

    A. Social

    B. Regulatory

    C. Environmental

    D. Governmental

  • Question 20:

    Which of the following should be considered first when determining the privacy management for project data?

    A. Evaluating the current privacy protection program

    B. Understanding applicable privacy regulations

    C. Maintaining awareness of industry best practices

    D. Implementing security role-based controls

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.