During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
A. Obtain details from the owner of the project.
B. Update the critical path for the project.
C. Apply contingency reserves.
D. Reestimate epic user stories.
A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?
A. Use an on-premises project management scheduling tool.
B. Limit access to members of the project team.
C. Mandate overtime to get the project completed sooner.
D. Ensure all team members have signed a non-disclosure agreement.
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?
A. Buy a replacement for the faulty equipment.
B. Get the maintenance team to resolve the issue.
C. Escalate the issue to the project sponsor.
D. Rate the severity of the impact the issue has on the project.
A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the
communicated expectations.
Which of the following tools should the project manager use to validate the functionality?
A. Project status report
B. Requirements Traceability Matrix
C. Detect log
D. Signed project charter
E. Work breakdown structure
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
A. Implement the change.
B. Approve the test plan.
C. Notify customers.
D. Develop a rollback plan.
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
A. Update the work breakdown structure.
B. Review the backlog.
C. Seek baseline approval.
D. Establish the resource pool.
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
A. Validate against the scope statement and ask for sign-off.
B. Run a control chart to ensure the quality of the deliverables.
C. Review the risk register and close up residual risks.
D. Start the training and handoff for the operations team.
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
A. Scope of work
B. Request for proposal
C. Vendor rules of engagement
D. Project schedule
How does data discovery assist with data classification?
A. It shows where specific data is stored
B. It automatically classifies data by keywords
C. It helps to identify the data owner
D. It provides assurance of data integrity
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
A. Performing
B. Adjourning
C. Forming
D. Norming
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.