  • Question 21:

    A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

    A. Planning

    B. Initiating

    C. Controlling

    D. Executing

  • Question 22:

    Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the

    meeting on another day.

    Which of the following techniques is the project manager using?

    A. Avoiding

    B. Smoothing

    C. Forcing

    D. Compromising

  • Question 23:

    A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

    A. Escalate the communication issues.

    B. Implement a communication platform.

    C. Review the communication plan.

    D. Talk with the head of the PMO.

  • Question 24:

    Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

    A. Memorandum of understanding

    B. Request for information

    C. Statement of work

    D. Non-disclosure agreement

  • Question 25:

    A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

    Which of the following is the current status of the process?

    A. Based on the rule of seven, the process is under control

    B. The amount of data is insufficient to determine if quality is low.

    C. The process is out of control and should be revised.

    D. The goal should be adjusted since most of the data points are close to the lower limit.

  • Question 26:

    A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

    A. Request a change control ticket.

    B. Review the schedule plan.

    C. Refine the project documentation.

    D. Revise the communication plan.

  • Question 27:

    During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

    A. Awareness of the local environment

    B. Awareness of the brand value

    C. Awareness of the resource constraints

    D. Awareness of the company's mission

  • Question 28:

    A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

    A. Quality assurance

    B. Organizational branding restrictions

    C. State privacy acts

    D. Country legal regulations

  • Question 29:

    A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

    A. Creation of a social news forum

    B. Management directives to use the new system

    C. New user kickoff meeting

    D. Monthly feedback and training sessions

  • Question 30:

    A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

    A. laaS

    B. XaaS

    C. PaaS

    D. SaaS

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.