  • Question 31:

    During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to

    analyze and determine whether the particular cause and effect are related by using one of the following charts.

    Which of the following should the team use?

    A. Option A

    B. Option B

    C. Option C

    D. Option D

  • Question 32:

    As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

    A. Document the request in the change control log.

    B. Communicate the change deployment.

    C. Conduct an impact assessment.

    D. Implement the change.

  • Question 33:

    In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

    A. Developing a RACI

    B. Identifying and assessing stakeholders

    C. Assigning project resources

    D. Establishing communication channels

  • Question 34:

    While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

    A. It highlights the performance issues of the project manager and team members.

    B. It lets the project manager know which stakeholders are allies for future projects.

    C. It helps the project manager create a more structured lessons-learned session.

    D. It identifies the stakeholders' real opinions about the project.

  • Question 35:

    Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

    A. Service-level agreement

    B. Functional testing

    C. Warranty period

    D. Audit

  • Question 36:

    Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

    A. Assign action items to attendees.

    B. Distribute an agenda.

    C. Email the minutes from the previous meeting.

    D. Schedule a convenient time.

  • Question 37:

    A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

    A. Forming, storming, performing, norming, adjourning

    B. Forming, performing, storming, norming, adjourning

    C. Forming, norming, storming, performing, adjourning

    D. Forming, storming, norming, performing, adjourning

  • Question 38:

    After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

    A. Continuous integration

    B. Rollback plan

    C. Customer notification

    D. Automated testing

  • Question 39:

    A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

    A. Mitigate

    B. Transfer

    C. Accept

    D. Share

  • Question 40:

    Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

    A. Escalate directly to the project sponsor

    B. Push the kickoff meeting out by one week

    C. Proceed with the kickoff as planned

    D. Identity replacements for project stakeholders

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.