  • Question 71:

    A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

    Based on the chart, which of the following is the current status of the project?

    A. Behind schedule and over budget

    B. Behind schedule and under budget

    C. Ahead of schedule and over budget

    D. Ahead of schedule and under budget

  • Question 72:

    Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

    A. Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

    B. Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

    C. Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

    D. Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

  • Question 73:

    During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

    A. Determine budget constraints.

    B. Validate the business case.

    C. Update the project charter.

    D. Create a project schedule

  • Question 74:

    Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

    A. Compromising

    B. Forcing

    C. Smoothing

    D. Collaborating

  • Question 75:

    The executive sponsor asks a project manager to summarize the following for a project:

    1.

    Final capital expenditures.

    2.

    Anticipated cost of new employee resources to support the solution.

    3.

    Maintenance estimates.

    Which of the following information should the project manager provide?

    A. Cost baseline

    B. Burn rate

    C. Cost variance report

    D. Total project cost

  • Question 76:

    A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

    A. Make an impact assessment.

    B. Prepare a new purchase order.

    C. Select a new vendor.

    D. Create a risk register.

  • Question 77:

    Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

    A. Kanban board

    B. Pareto chart

    C. Ishikawa diagram

    D. Decision tree

  • Question 78:

    A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

    A. ROI.

    B. SOW.

    C. RFI.

    D. RPR

  • Question 79:

    A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

    A. Train users on the proper use of the system.

    B. Escalate the issue to the CCB

    C. Hold sessions to understand user challenges.

    D. Track system usage and report user activity.

    E. Log the issue in the project risk register.

    F. Create a memorandum of acceptable use.

  • Question 80:

    A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

    A. Use only full-time employees even if the project is delayed.

    B. Hire all team members to avoid any delay in the project.

    C. Close the contract and pay the contractors cash for the remainder of the project.

    D. Look for an overseas vendor to finalize the project work.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.