PMI PMI Certifications CAPM Questions & Answers

  • Question 1231:

    Which of the following items is a technique for data gathering?

    A. Facilitation

    B. Meeting management

    C. Conflict management

    D. Interviews

  • Question 1232:

    Which actions should a project manager follow to manage stakeholders?

    A. Identify the key stakeholders and keep them informed at all times.

    B. Identify the stakeholders, planning, managing and monitoring their engagement

    C. Meet and keep informed any person related to the project, at all times

    D. Identify the stakeholders and monitor their level of satisfaction

  • Question 1233:

    It's time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

    A. Pareto chart

    B. Regression analysis

    C. Statistical sampling

    D. Automated testing tools

  • Question 1234:

    What is the purpose of the Manage Quality process?

    A. To translate the quality management plan into executable quality activities

    B. To monitor and record the results of executed quality management activities

    C. To determine if project activities comply with organizational and project policies.

    D. To identify project deliverables and quality requirements and/or standards

  • Question 1235:

    What do top project managers do to maximize their sphere of influence within a project team?

    A. Consider management standards, economic factors, and sustainability strategies

    B. Contribute knowledge and expertise to others within the profession

    C. C Address political and strategic issues that impact the project's viability or quality

    D. D Demonstrate superior relationship and communication skills while displaying a positive attitude

  • Question 1236:

    The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

    What is the outcome of the duration of this task'?

    A. The task will be completed on time.

    B. The task will not be completed on time.

    C. Activity A is not a critical path task

    D. The precedence diagram cannot be used to provide answers for duration calculations

  • Question 1237:

    A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?

    A. Key stakeholders are regularly involved

    B. Key stakeholders are continuously involved

    C. Key stakeholders are involved at specific milestones

    D. Key stakeholders are always involved

  • Question 1238:

    To ensure stakeholder satisfaction; identified stakeholder needs should all be:

    A. Vetted

    B. Ranked from greatest to least

    C. Qualified

    D. Documented in the stakeholder engagement plan

  • Question 1239:

    A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project.

    What specific area of quality, is the project team choosing for tailoring?

    A. Policy compliance and auditing

    B. Standards and compliance

    C. Review of lessons learned

    D. Test and inspection planning

  • Question 1240:

    What CPI > 1 and SPI < 1 mean?

    A. Under budget ahead of schedule

    B. Over budget, behind schedule

    C. Under budget, behind schedule

    D. Over budget, ahead of schedule

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.