  • Question 81:

    You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.

    How can you fulfill these requirements in SAP ECC? (Choose two)

    A. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.

    B. Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

    C. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

    D. Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

  • Question 82:

    Which of the following scheduling types can only be used in capacity planning?

    A. Midpoint

    B. Forward

    C. Only capacity requirements

    D. Backward

  • Question 83:

    Which of the following features are offered by MRP areas in SAP ECC? (Choose two)

    A. A storage location may be assigned to different MRP areas.

    B. An MRP area may include different storage locations.

    C. Make-to-order production is supported by storage location MRP areas.

    D. Subcontracting is supported by MRP areas.

  • Question 84:

    Which function is supported by production orders?

    A. Automatic selection of a work center at order release

    B. Automatic creation of transfer orders at order release

    C. Automatic reading of PP master data at order release

    D. Automatic printing of order documents at order creation

  • Question 85:

    Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)

    A. Automatic generation of a transport order

    B. Material directory

    C. Pull list

    D. Pick list

    E. Logistics Information System (LIS)

  • Question 86:

    In which of the following objects can you activate back flushing for production orders? (Choose three)

    A. Work center

    B. Routing

    C. Material master (finished product)

    D. Material master (component)

    E. Production scheduling profile

  • Question 87:

    You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).

    Which of the following properties for the resulting dependent requirements applies?

    A. In multi-level backward scheduling, dependent requirements are calculated to the exact second.

    B. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.

    C. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

    D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

  • Question 88:

    A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.

    What do you have to consider for the two lists at this stage? (Choose two)

    A. The stock/requirements list was updated the moment it was accessed.

    B. The MRP list displays the production order.

    C. The MRP list has the status "processed".

    D. The stock/requirements list displays the production order.

  • Question 89:

    When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.

    What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?

    A. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in Customizing.

    B. Set up the planning files in Customizing and specify the plant parameters for plant 1000 in Customizing of the MRP group.

    C. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in the MRP views in material master.

    D. Activate requirements planning in Customizing for MRP areas in plant 1000 and specify the plant parameters for plant 1000 in the MRP views in material master.

  • Question 90:

    Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

    A. Rescheduling the operation

    B. Posting the goods receipt for the production order

    C. Confirming the operation

    D. Setting the status technically complete (TECO)

    E. Reducing the order quantity

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.