Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
A. Sprint retrospective
B. Sprint review
C. Sprint planning
D. Daily Scrum
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
A. Rollback plan
B. Downtime stage
C. Maintenance window
D. Validation checks
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?
A. Too much time might be spent generating project delays.
B. The project manager might be seen as weak.
C. The number of change requests throughout the project might be reduced.
D. Some stakeholders might not be completely satisfied.
Which of the following describes KPIs?
A. Analyses of organizational strengths and weaknesses
B. Graphical representations of process flow
C. Elements against which performance can be measured
D. Collaboration platform tools
Which of the following describes some of the features of the Agile methodology?
A. It uses a direct approach, Gantt charts, and a ticketing system.
B. It uses an indirect approach, spreadsheets for documentation, and change request documents.
C. It uses an iterative approach, backlogs, and burndown charts.
D. It uses a step-by approach, an issue log, and pie charts.
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
A. Discovery
B. Execution
C. Initiating
D. Planning
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
A. Validation check
B. Downtime window schedule
C. Customer notifications
D. Risk analysis
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
A. Forcing
B. Avoiding
C. Compromising
D. Smoothing
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
A. Update the WBS.
B. Escalate to the CCB.
C. Accept the change.
D. Implement the change.
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?
A. Assign a scribe to take notes.
B. Record the meeting and transcribe the notes later.
C. Instruct each team member to take notes.
D. Get a facilitator for the meetings.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.