During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?
A. Issue log
B. Risk register
C. Defect log
D. Traceability matrix
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
A. Pareto
B. Run
C. Control
D. Histogram
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
A. Dashboard
B. Gantt chart
C. Work breakdown structure
D. Requirements Traceability Matrix
Which of the following items must be protected as Pll? (Select TWO).
A. Job title
B. Home address
C. Work phone number
D. Time zone
E. Date of birth
F. Blood type
A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?
A. Gantt chart
B. Project organization chart
C. Program Evaluation Review Technique chart
D. Milestone chart
Which of the following statements best describes a content management system?
A. A system to manage electronic signatures and document workflow
B. A system to manage database integration and provide messaging services
C. A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish
D. A system to manage documents archival, such as emails, spreadsheets, and support tickets
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
A. Create a list of tasks and share it with the team.
B. Resend the scope of work to the team.
C. Review the Gantt chart weekly with the team.
D. Have the project sponsor meet with the team.
Which of the following can a project manager infer from the following velocity chart?
A. The project is on schedule.
B. The project Is ahead of schedule.
C. The project is behind schedule.
D. The project is at risk.
Which of the following is the main reason for documenting artifacts?
A. To provide a record of the project's progress and achievements for future reference
B. To show stakeholders that the project is on track and progressing as planned
C. To help team members be aware of roles and responsibilities
D. To ensure that the project team understands the importance of the project to the organization
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
A. RFI
B. RFP
C. RFQ
D. RFB
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.