SAP SAP Certifications C_TS412_2021 Questions & Answers

  • Question 21:

    What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question

    A. Location

    B. Material

    C. Production version

    D. Resource

  • Question 22:

    You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

    A. The person responsible for the work center

    B. The person responsible for the superior WBS element

    C. The MRP controller for the network

    D. The person responsible for the network activity

  • Question 23:

    The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?

    A. Free planning

    B. Top-down

    C. Strict bottom-up

    D. Bottom-up

  • Question 24:

    You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

    A. Network profile

    B. Data entry profile

    C. Project profile

    D. Network type

  • Question 25:

    You are working with networks and WBS elements. Which of the following statements applies

    A. You can reassign an activity from one network to another

    B. You can assign the network header to multiple WBS elements

    C. You have to maintain a network profile in the project profile

    D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.

  • Question 26:

    Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

    A. Usage of cost elements is mandatory

    B. Sales prices are maintained in the DIP profile

    C. DIP is used to create a quotation

    D. Sources can be based on line items

    E. Material determination is mandatory

  • Question 27:

    In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

    A. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

    B. The purchase order is updated automatically to match the new quantity while saving the project.

    C. A workflow can be triggered to inform the purchasing group.

    D. The system automatically creates a new purchase requisition with the difference to the original quantity

  • Question 28:

    A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

    A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element

    B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing

    C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element

    D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

  • Question 29:

    When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

    A. Service specification

    B. Overall limit (maximum value of all unplanned services)

    C. Service purchase order number

    D. Material master within service specification

    E. Vendor

  • Question 30:

    Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question

    A. Basic dates

    B. Forecast dates

    C. Baseline dates

    D. Planned dates

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS412_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.