Exam Details

  • Exam Code
    :C_TS412_2021
  • Exam Name
    :SAP Certified Associate - SAP S/4HANA Project Systems
  • Certification
    :SAP Certifications
  • Vendor
    :SAP
  • Total Questions
    :110 Q&As
  • Last Updated
    :Mar 24, 2025

SAP SAP Certifications C_TS412_2021 Questions & Answers

  • Question 101:

    Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.

    What is the requisites for implement scheduling of events?

    A. Priority of events must be set.

    B. Scheduling parameters for material scheduling must be set.

    C. Events must be released manually.

    D. Event scenarios must be defined.

  • Question 102:

    How can you confirm the working hours of different work centers for a single activity?

    A. Create multiple confirmations for the activity and use the appropriate work center for each confirmation

    B. Enter direct activity allocation assigning multiple work centers

    C. Enter multiple work centers within a single confirmation D. Assign multiple work centers to the activity

  • Question 103:

    Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

    A. The materials must allow sales order or project stock

    B. The exact lot size procedure must be used

    C. The procurement type of the material must be internal

    D. An MRP group must be assigned

  • Question 104:

    You want to use subnetworks during the project. Which of the following statements describes subnetworks?

    A. Maintenance orders can be defined as sub-network

    B. The scheduling type of a subnetwork is always copied from the superior network

    C. A subnetwork cannot be defined for a superior subnetwork.

    D. Subnetworks must be scheduled separately from the superior network

  • Question 105:

    How can you update the degree of processing for an activity?

    A. By using results analysis

    B. By changing the activity

    C. By scheduling the activity

    D. By confirming the activity

  • Question 106:

    You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

    A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

    B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

    C. You can always maintain the actual start and finish date of a WBS element

    D. You can only maintain the actual start of a WBS element if the finish date is not maintained

  • Question 107:

    What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question

    A. A dynamic item processor (DIP) profile with the appropriate settings

    B. Released WBS elements, activities, and/or activity elements

    C. A header-account-assigned network that is assigned to a sales order item

    D. An activity-account-assigned network that is assigned to a sales order item

  • Question 108:

    Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

    A. Network profile

    B. Project profile

    C. Parameters for the network type

    D. Network type

  • Question 109:

    Revenues and Payment

    A customer use cross-company-code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

    A. Settle the WBS element to the highest billing element before you do the result analysis.

    B. Split the project intdifferent project according to each company code.

    C. Change the project structure so that it correspond better to the company's organization structure.

    D. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

  • Question 110:

    You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

    A. The manual hierarchical revenue planning will be displayed only if expert mode is activated

    B. The manual hierarchical revenue planning has no reference to cost elements

    C. Cost element reports can display costs but not revenues

    D. Cost element reports display integrated planning only

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS412_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.