  • Question 41:

    You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

    A. The formula for costing in the work center is incorrect

    B. The activity output price for the activity type and cost center assigned to the work center is not maintained.

    C. The duration is missing in the activity

    D. The Determine Costs indicator in the network header rules out planned cost calculation

    E. Integrated planning for the network is active

  • Question 42:

    You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?

    A. Missing budget for material components

    B. Missing reservations for material components

    C. Missing material availability

    D. Missing authorizations to release material components

  • Question 43:

    Where do you control whether a project stock is managed as valuated or non-valuated project stock?

    A. In the network activity

    B. In the project definition

    C. In the WBS element

    D. In the material master

  • Question 44:

    Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

    A. Project-relevant purchase orders

    B. Capacity requirements

    C. Maintenance orders assigned to an activity

    D. Production orders assigned to WBS elements

  • Question 45:

    You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

    A. If the maximum reduction level is less than 100

    B. If the reduction strategy is set in the network header

    C. If the reduction strategy is set in each activity

    D. If the appropriate reduction type is set in the parameters for network scheduling

  • Question 46:

    Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

    A. Schedule Manager

    B. Project Builder

    C. Project planning board

    D. Easy Cost Planning

  • Question 47:

    Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

    A. Material master

    B. Network activity

    C. WBS element

    D. BOM item

  • Question 48:

    You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?

    Note : there are 2 correct answers for this question.

    A. The procurement type in the material master is set to in-house Production.

    B. The item category of the materials is set tstock item.

    C. The material have no material number.

    D. The item category of the materials is set tnon-stock item.

  • Question 49:

    Cost and Budget

    What function are available for period end-closing in the project System?

    A. Result analysis

    B. Progress analysis

    C. Milestone trend analysis

    D. Settl ement

    E. Confirmation

  • Question 50:

    Project Structure

    Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.

    What standard report do you recommend?

    A. Structure overviews for budget.

    B. Cost element report on budget updates.

    C. Line item report for budget

    D. Hierarchical report on budget updates.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS412_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.