  • Question 121:

    A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed- upon date. Which of the following should the project manager do first?

    A. Hold the project until the devices are delivered.

    B. Evaluate the impact to baselines.

    C. Request another supplier to ship devices.

    D. Update the project timeline with a new project end date.

  • Question 122:

    Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

    A. Risk

    B. Change

    C. Defect

    D. Issue

  • Question 123:

    A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

    A. Meet with the team and highlight the importance of change management.

    B. Roll back the process and submit a change request.

    C. Document the event as a lesson learned.

    D. Remove the team member who bypassed the CCB process.

  • Question 124:

    During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

    A. Status report

    B. Issue log

    C. Risk report

    D. Risk register

  • Question 125:

    Which of the following activities are important parts of the closing phase? (Select two).

    A. Releasing resources

    B. Locking risks

    C. Updating stakeholder register

    D. Closing contracts

    E. Completing the work breakdown structure

    F. Negotiating the next project

  • Question 126:

    Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

    A. Exploit

    B. Share

    C. Transfer

    D. Accept

  • Question 127:

    A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

    A. Key stakeholder identification

    B. Preliminary procurement

    C. Solution design determination

    D. Critical factor enlistment

  • Question 128:

    Which of the following statements best represents a network issue?

    A. The development team on the fourth floor is unable to access servers and email services.

    B. Cell phones served by a specific telecom company are getting a "no service" message.

    C. A user cannot connect to Wi-Fi because of a wrong ID or password.

    D. A user is receiving an automatic reply message saying that an email address does not exist.

  • Question 129:

    Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

    A. SaaS

    B. IaaS

    C. DaaS

    D. PaaS

  • Question 130:

    A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

    A. Performance

    B. Smoke

    C. Regression

    D. Unit

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.