Which of the following describes three-tier architecture?
A. Conceptual, design, and implementation stages
B. Presentation, application, and data processing
C. Network, software, and security
D. Development, testing, and production environment
Which of the following aspects are true of agile as compared to waterfall? (Select two).
A. Agile works through larger integrated teams.
B. Agile promotes project manager ownership over deliverables.
C. Agile reinforces the importance of comprehensive documentation.
D. Agile has more customer involvement throughout development.
E. Agile is more flexible to allow for changes in scope.
F. Agile is comprised of well-defined phases.
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
A. Transfer
B. Avoid
C. Accept
D. Mitigate
Which of the following are primary features provided by a standard laaS solution? (Select two).
A. Encryption
B. Storage
C. Networking
D. User interface
E. Access
F. Database
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
A. Remove the team member's access.
B. Release the project resources.
C. Collect the stakeholders' feedback.
D. Have the closeout report approved.
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A. Lessons learned
B. Risk analysis
C. Removing resources
D. Acquiring resources
E. Statement of work sign-off
F. Stakeholder analysis
G. Removing access
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
A. Time to be fixed
B. Impact to project
C. Issue category
D. Resource availability
Which of the following tools is best to use for storing lessons learned?
A. Whiteboard
B. Wiki knowledge base
C. Content management system D. Workflow platform
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
A. Creating a backlog
B. Managing the quality of deliverables
C. Updating the issue log
D. Performing a risk assessment
E. Validating the deliverables
F. Reconciling the project budget
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
A. Project change management plan
B. Project management plan
C. Project transition plan
D. Project communication plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.