  • Question 241:

    A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

    A. Review the detailed plan.

    B. Develop a preliminary scope.

    C. Develop a transition plan.

    D. Develop a project management plan.

    E. Review the resource pool.

    F. Review the project objectives.

  • Question 242:

    A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

    A. Project network diagram

    B. Gantt chart

    C. Issue log

    D. Risk report

  • Question 243:

    A visual that displays team progress was created for stand-up meetings.

    Which of the following BEST describes what is being represented on the visual?

    A. Decision board

    B. Whiteboard

    C. Task board

    D. Dashboard

  • Question 244:

    A team member identifies a critical issue in production. Which of the following should the project manager apply?

    A. Compliance check

    B. Release plan

    C. Rollback plan

    D. Validation check

  • Question 245:

    A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

    A. Assign more resources to complete similar stories in the future.

    B. Break the stories into workable items that can be completed within one sprint.

    C. Extend the sprint duration when required with the approval of the product owner.

    D. Release the current progress into production and carry over the rest of the code for the next sprint.

  • Question 246:

    Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

    A. Start-to-start

    B. Start-to-finish

    C. Finish-to-finish

    D. Finish-to-start

  • Question 247:

    During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

    A. Work with the project scheduler to update the project timeline.

    B. Communicate to the stakeholders about the updated timeline.

    C. Ask the development team to fast-track upcoming activities.

    D. Add two resources so the critical activities will finish on time.

  • Question 248:

    During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

    A. Issue log

    B. Defect log

    C. Change log

    D. Task board

  • Question 249:

    A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

    A. Company vision

    B. Global environment

    C. Brand value

    D. Mission statement

    E. Portfolio budget

    F. Local legislation

  • Question 250:

    During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

    A. Schedule

    B. Status report

    C. Issue log

    D. Task board

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.