A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps. Which of the following actions should the project manager take?
A. Notify customers the downtime will take longer than expected.
B. Add new team members to help speed up validation.
C. Begin executing the rollback plan.
D. Record the issue and proceed with the implementation.
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
A. External
B. Internal
C. Mandatory
D. Discretionary
A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?
A. Escalate to vendor management.
B. Consult the request for proposal.
C. Review the meeting cadence.
D. Reinforce the rules of engagement.
Which of the following tools is best to use when conducting project meetings across time zones?
A. Text
B. Calendaring tools
C. Videoconference
D. Email
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
A. Collate the lessons learned.
B. Perform a gap analysis.
C. Review existing artifacts.
D. Conduct a retrospective.
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
A. The project manager did not release the resources.
B. The project is in the verification testing phase.
C. The project manager did not complete the project closure phase.
D. The project manager did not remove access.
Which of the following would be considered operational security?
A. Mobile device compliance
B. Background screening
C. Multifactor authentication
D. Facility access
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
A. Data plan
B. Contingency plan
C. Rollback plan
D. Recovery plan
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
Two developers High uncertainty about existing systems Risk of frequent requirement changes Tight deadlines
Which of the following project methodologies would be best to use in this situation?
A. PRINCE2
B. Scrum
C. SAFe
D. XP
A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?
A. Milestone chart
B. Gantt chart
C. PERT chart
D. WBS
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.