  • Question 281:

    A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

    A. Resource allocation

    B. Communication security

    C. Technological factors

    D. Cultural differences

  • Question 282:

    After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

    A. Smoke test

    B. Stress test

    C. Penetration test

    D. Regression test

  • Question 283:

    A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

    A. Flat

    B. Projectized

    C. Weak matrix

    D. Functional

  • Question 284:

    Which of the following provides the best justification for undertaking a project?

    A. Scope statement

    B. Business case

    C. Sponsor request

    D. Project charter

  • Question 285:

    A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

    A. laaS

    B. XaaS

    C. PaaS

    D. SaaS

  • Question 286:

    During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead

    highlighted that this functionality request was rejected during the planning phase.

    Which of the following documents is the best source for the PM to use to confirm this assertion?

    A. Issue log

    B. Scope statement

    C. Risk report

    D. Change log

  • Question 287:

    An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

    A. Enterprise resource planning and end user applications

    B. Electronic document and record management systems

    C. Customer relationship management and databases

    D. Content management and financial systems

  • Question 288:

    Which of the following BEST describes how an organization should coordinate management of multiple related projects?

    A. Apply the SDLC process.

    B. Establish a program.

    C. Consult the CCB.

    D. Use different frameworks

  • Question 289:

    A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

    A. Encryption

    B. Multifactor authentication

    C. Quality assurance

    D. Password protection

  • Question 290:

    A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

    Purpose Scope of work Location of work Period of performance Deliverables schedule Applicable standards Acceptance criteria Special requirements Payment schedule

    Which of the following documents did the client provide to the project manager?

    A. RFP

    B. WBS

    C. SLA

    D. SOW

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.